Paragraph 13 Operational environmental management planI1
England, Wales and Scotland As made
Prior to the date of final commissioning for any part of the authorised development, an operational environmental management plan for that part must be submitted to and approved by the relevant planning authority or, where the part falls within the administrative area of multiple relevant planning authorities, each of the relevant planning authorities, in consultation with the relevant highway authority, the relevant waste authority, the Environment Agency, Natural England, and where the part falls within its administrative area, Lincolnshire County Council.
The operational environmental management plan must be substantially in accordance with the framework operational environmental management plan.
The operational environmental management plan must be implemented as approved and maintained throughout the operation of the relevant parts of the authorised development to which the plan relates.
Annotations
Commencement
- I1
Sch. 2 para. 13 in force at 5.11.2025, see art. 1