OpenLegislation

Section 61Z Wales: requirement to carry out pre-application consultationF1

(1)

This section applies where—

(a)

a person (the “applicant”) proposes to make an application for planning permission for the development of land within the area of a local planning authority in Wales, and

(b)

the proposed development is development of a description specified in a development order.

(2)

The applicant must carry out consultation on the proposed application in accordance with subsections (3) and (4).

(3)

The applicant must publicise the proposed application in such manner as the applicant reasonably considers likely to bring it to the attention of a majority of the persons who own or occupy premises in the vicinity of the land.

(4)

The applicant must consult each specified person about the proposed application.

(5)

Publicity under subsection (3) must—

(a)

set out how the applicant may be contacted by persons wishing to comment on the proposed development;

(b)

give such information about the proposed timetable for the consultation as is sufficient to ensure that persons wishing to comment on the proposed development may do so in good time.

(6)

For the purposes of subsection (4), a specified person is a person specified in, or a person of a description specified in, a development order.

(7)

Subsection (2) does not apply—

(a)

if the proposed application is an application under section 293A, or

(b)

in cases specified in a development order.

(8)

A development order may make provision about, or in connection with, consultation required to be carried out under this section (including by way of publicising an application under subsection (3)).

(9)

That provision may include —

(a)

provision about how the consultation is to be carried out (including about the form and content of documents, and information and other materials that are to be provided to a person for the purposes of, or in connection with, the consultation);

(b)

provision about responding to the consultation (including provision requiring a person consulted to respond to the consultation, or to respond to the consultation in a particular way, or to respond within a particular time);

(c)

provision about the timetable (including deadlines) for consultation;

(d)

provision for a person consulted by virtue of subsection (4) to make a report to the Welsh Ministers about the person's compliance with any requirement imposed by virtue of paragraph (b) or (c) (including provision as to the form and content of the report and the time at which it is to be made).

Annotations

Textual amendments

F1

S. 61Z and cross-heading inserted (6.9.2015 for specified purposes, 1.3.2016 in so far as not already in force) by Planning (Wales) Act 2015 (anaw 4), ss. 17(2), 58(2)(b)(4)(b); S.I. 2016/52, art. 2(a) (with art. 6)

Notes on Part III

Modifications

C1

Pt. 3 (ss. 55-106) except ss. 76, 90(2)(5) applied (with modifications) (17.7.1992) by S.I. 1992/1492, regs. 2(1)(b), 3-11

Pt. 3 (ss. 55-106): power to modify conferred (10.11.1993) by 1993 c. 28, s. 171(1)(a); S.I. 1993/2762, art. 3

Pt. 3 (ss. 55-106) applied (5.11.1993) by 1993 c. 42, s. 24(1) (with ss. 2, 30(1), Sch. 2 para.9)

Pt. 3 (ss. 55-106) extended (1.11.1995) by 1995 c. 25, s. 96(2) (with ss. 7(6), 115, 117); S.I. 1995/2765, art. 2

Pt. 3 (ss. 55-106) modified (1.4.1996) by 1994 c. 19, s. 20(3), Sch. 5 Pt. III paras. 15(1), 20 (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2

Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 9(1)(2)

Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 51

Pt. 3 (ss. 55-106) modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), art. 20(1)

Pt. 3 (ss. 55-106) modified (31.10.2005) by The London Thames Gateway Development Corporation (Planning Functions) Order 2005 (S.I. 2005/2721), art. 4

Pt. 3 (ss. 55-106) modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), art. 21(1) (with arts. 3(5), 15(3))

Pt. 3 (ss. 55-106) applied (7.6.2006) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 89, 121, Sch. 4 para. 3(2) (with s. 111); S.I. 2006/1281, art. 2

Pt. 3 (ss. 55-106) modified (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), art. 17(1) (with art. 43)

Pt. 3 (ss. 55-106) modified (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), art. 18(1)

C2

Pt. 3 (ss. 55-106) modified (4.5.2005) by The Telford Railfreight Terminal (Donnington) Order 2005 (S.I. 2005/1163), art. 25(2) (with art. 30)

Pt. 3 modified (23.8.2007) by The Docklands Light Railway (Capacity Enhancement and 2012 Games Preparation) Order 2007 (S.I. 2007/2297), art. 17(1) (with arts. 3(6), 12(3))

C3

Pt. 3 modified (28.9.2007) by The London Gateway Logistics and Commercial Centre Order 2007 (S.I. 2007/2657), art. 27(1) (with art. 19, Sch. 3 para. 13(2))

C4

Pt. 3 modified (22.7.2008) by Crossrail Act 2008 (c. 18), s. 10(1)

C5

Pt. 3 modified (14.10.2008) by The Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), art. 34(1) (with art. 36(3))

C6

Pt. 3 modified (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), art. 28(1)

C7

Pt. 3 modified (27.8.2010) by The Llangollen and Corwen Railway Order 2010 (S.I. 2010/2136), art. 11(1)

C8

Pt. 3 applied (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 47(1) (with art. 51, Sch. 10 paras. 68, 85)

C9

Pt. 3 modified (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), arts. 1, 36(2)

C10

Pt. 3 applied (5.4.2017) by The Keuper Underground Gas Storage Facility Order 2017 (S.I. 2017/433), arts. 1, 38(2)

C11

Pt. 3 modified (11.1.2023) by The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022 (S.I. 2022/1406), arts. 1, 35(2) (with art. 34(2), Sch. 12 paras. 5, 47, 79)