Section 92A Extension of outline planning permission etc in event of legal challengeF1

Changes not yet applied. Later legislation changes this provision in ways not yet written into the text below:

(1)

This section applies where a person is given permission by a court to bring proceedings challenging the validity, in respect of the development of land in England, of—

(a)

a grant (or deemed grant) of outline planning permission, or

(b)

the approval of reserved matters under such a permission.

(2)

Any reserved matters application period or implementation period that is running when the court gives permission to bring the proceedings is extended by one year.

(3)

If a party to the proceedings is given permission to appeal to the Court of Appeal against a decision determining the challenge, any reserved matters application period or implementation period that is running at that time is extended by one year.

(4)

If a party to the proceedings is given permission to appeal to the Supreme Court against a decision determining the challenge, any reserved matters application period or implementation period that is running at that time is extended by two years.

(5)

Any extension of a period under subsection (2), (3) or (4) is to run concurrently with any other extension of the period under the same subsection (so far as they overlap).

(6)

Any extension of a period under subsection (3) is to run consecutively to the previous extension of the period under subsection (2) (if they would otherwise overlap).

(7)

Any extension of a period under subsection (4) is to run consecutively to the previous extension of the period under subsection (2) and any previous extension of the period under subsection (3) (if they would otherwise overlap).

(8)

For the purposes of subsections (2) to (4), an implementation period that is determined by reference to an approval of a reserved matter starts to run when the reserved matters application is made (and the reserved matters application period ceases to run at that point).

(9)

Subsection (10) applies if a reserved matters application is made without taking advantage of an extension under this section.

(10)

Any implementation period determined by reference to the approval sought by the reserved matters application is extended by the number of days by which the reserved matters application period is extended under this section.

(11)

Subsection (12) applies if a reserved matters application period is extended (or further extended) under this section and the reserved matters application is made taking advantage of the extension but before the end of the period as extended.

(12)

Any implementation period determined by reference to the approval sought by the reserved matters application is extended by the number of whole days remaining in the reserved matters application period (as extended) when the reserved matters application is made.

(13)

In this section—

  • “implementation period”, in relation to a grant of outline planning permission, means the period before the end of which development to which the permission relates must be begun (see section 92(2)(b), (4) and (5));

  • “outline planning permission” has the same meaning as in section 92;

  • “reserved matters application” means an application for the approval of a reserved matter in pursuance of section 92;

  • “reserved matters application period”, in relation to a grant of outline planning permission, means the period before the end of which a reserved matters application relating to the permission is required to be made (see section 92(2)(a), (4) and (5)).

(14)

In this section, references to determining a challenge are to determining it after a full hearing (and accordingly do not include a refusal of permission or leave).

Annotations

Textual amendments

F1

S. 92A inserted (18.2.2026) by Planning and Infrastructure Act 2025 (c. 34), ss. 56(3), 118(2)(e) (with ss. 56(7), 116)

Notes on Part III

Modifications

C1

Pt. 3 (ss. 55-106) except ss. 76, 90(2)(5) applied (with modifications) (17.7.1992) by S.I. 1992/1492, regs. 2(1)(b), 3-11

Pt. 3 (ss. 55-106): power to modify conferred (10.11.1993) by 1993 c. 28, s. 171(1)(a); S.I. 1993/2762, art. 3

Pt. 3 (ss. 55-106) applied (5.11.1993) by 1993 c. 42, s. 24(1) (with ss. 2, 30(1), Sch. 2 para.9)

Pt. 3 (ss. 55-106) extended (1.11.1995) by 1995 c. 25, s. 96(2) (with ss. 7(6), 115, 117); S.I. 1995/2765, art. 2

Pt. 3 (ss. 55-106) modified (1.4.1996) by 1994 c. 19, s. 20(3), Sch. 5 Pt. III paras. 15(1), 20 (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2

Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 9(1)(2)

Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 51

Pt. 3 (ss. 55-106) modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), art. 20(1)

Pt. 3 (ss. 55-106) modified (31.10.2005) by The London Thames Gateway Development Corporation (Planning Functions) Order 2005 (S.I. 2005/2721), art. 4

Pt. 3 (ss. 55-106) modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), art. 21(1) (with arts. 3(5), 15(3))

Pt. 3 (ss. 55-106) applied (7.6.2006) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 89, 121, Sch. 4 para. 3(2) (with s. 111); S.I. 2006/1281, art. 2

Pt. 3 (ss. 55-106) modified (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), art. 17(1) (with art. 43)

Pt. 3 (ss. 55-106) modified (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), art. 18(1)

C2

Pt. 3 (ss. 55-106) modified (4.5.2005) by The Telford Railfreight Terminal (Donnington) Order 2005 (S.I. 2005/1163), art. 25(2) (with art. 30)

Pt. 3 modified (23.8.2007) by The Docklands Light Railway (Capacity Enhancement and 2012 Games Preparation) Order 2007 (S.I. 2007/2297), art. 17(1) (with arts. 3(6), 12(3))

C3

Pt. 3 modified (28.9.2007) by The London Gateway Logistics and Commercial Centre Order 2007 (S.I. 2007/2657), art. 27(1) (with art. 19, Sch. 3 para. 13(2))

C4

Pt. 3 modified (22.7.2008) by Crossrail Act 2008 (c. 18), s. 10(1)

C5

Pt. 3 modified (14.10.2008) by The Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), art. 34(1) (with art. 36(3))

C6

Pt. 3 modified (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), art. 28(1)

C7

Pt. 3 modified (27.8.2010) by The Llangollen and Corwen Railway Order 2010 (S.I. 2010/2136), art. 11(1)

C8

Pt. 3 applied (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 47(1) (with art. 51, Sch. 10 paras. 68, 85)

C9

Pt. 3 modified (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), arts. 1, 36(2)

C10

Pt. 3 applied (5.4.2017) by The Keuper Underground Gas Storage Facility Order 2017 (S.I. 2017/433), arts. 1, 38(2)

C11

Pt. 3 modified (11.1.2023) by The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022 (S.I. 2022/1406), arts. 1, 35(2) (with art. 34(2), Sch. 12 paras. 5, 47, 79)