Section 93H Completion noticesF1
England and Wales
This section applies where—
a planning permission relating to land in England is by virtue of section 91 or 92 subject to a condition that the development to which the permission relates must begin before the expiration of a particular period, and development has been begun within that period but has not been completed,
development has begun in accordance with a simplified planning zone scheme in England but has not been completed by the time the area ceases to be a simplified planning zone,
development has begun in accordance with planning permission under an enterprise zone scheme in England but has not been completed by the time the area ceases to be an enterprise zone,
a planning permission under a neighbourhood development order is subject to a condition that the development to which the permission relates must begin before the expiration of a particular period, and development has begun within that period but has not been completed, or
a planning permission under a street vote development order is subject to a condition that the development to which the permission relates must begin before the expiration of a particular period, and development has begun within that period but has not been completed.
If the local planning authority are of the opinion that the development will not be completed within a reasonable period, they may serve a notice (a “completion notice”) stating that the planning permission will cease to have effect at a specified time (the “completion notice deadline”).
A completion notice must include—
prescribed information in relation to the right of appeal against the notice, and
any other prescribed information.
A completion notice must be served on—
the owner of the land,
if different, the occupier of the land, and
The local planning authority may withdraw a completion notice at any time before the completion notice deadline.
If they do so they must immediately give notice of the withdrawal to every person who was served with the completion notice.
If it appears to the Secretary of State to be expedient that a completion notice should be served in respect of any land in England, the Secretary of State may, after consulting the local planning authority, serve such a notice.
Annotations
Textual amendments
- F1
Ss. 93H-93J and cross-heading inserted (26.12.2023 for specified purposes) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 112(2), 255(3) (with ss. 112(4)(5), 247)
Notes on Part III
Modifications
- C1
Pt. 3 (ss. 55-106) except ss. 76, 90(2)(5) applied (with modifications) (17.7.1992) by S.I. 1992/1492, regs. 2(1)(b), 3-11
Pt. 3 (ss. 55-106): power to modify conferred (10.11.1993) by 1993 c. 28, s. 171(1)(a); S.I. 1993/2762, art. 3
Pt. 3 (ss. 55-106) applied (5.11.1993) by 1993 c. 42, s. 24(1) (with ss. 2, 30(1), Sch. 2 para.9)
Pt. 3 (ss. 55-106) extended (1.11.1995) by 1995 c. 25, s. 96(2) (with ss. 7(6), 115, 117); S.I. 1995/2765, art. 2
Pt. 3 (ss. 55-106) modified (1.4.1996) by 1994 c. 19, s. 20(3), Sch. 5 Pt. III paras. 15(1), 20 (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2
Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 9(1)(2)
Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 51
Pt. 3 (ss. 55-106) modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), art. 20(1)
Pt. 3 (ss. 55-106) modified (31.10.2005) by The London Thames Gateway Development Corporation (Planning Functions) Order 2005 (S.I. 2005/2721), art. 4
Pt. 3 (ss. 55-106) modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), art. 21(1) (with arts. 3(5), 15(3))
Pt. 3 (ss. 55-106) applied (7.6.2006) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 89, 121, Sch. 4 para. 3(2) (with s. 111); S.I. 2006/1281, art. 2
Pt. 3 (ss. 55-106) modified (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), art. 17(1) (with art. 43)
Pt. 3 (ss. 55-106) modified (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), art. 18(1)
- C2
Pt. 3 (ss. 55-106) modified (4.5.2005) by The Telford Railfreight Terminal (Donnington) Order 2005 (S.I. 2005/1163), art. 25(2) (with art. 30)
Pt. 3 modified (23.8.2007) by The Docklands Light Railway (Capacity Enhancement and 2012 Games Preparation) Order 2007 (S.I. 2007/2297), art. 17(1) (with arts. 3(6), 12(3))
- C3
Pt. 3 modified (28.9.2007) by The London Gateway Logistics and Commercial Centre Order 2007 (S.I. 2007/2657), art. 27(1) (with art. 19, Sch. 3 para. 13(2))
- C4
Pt. 3 modified (22.7.2008) by Crossrail Act 2008 (c. 18), s. 10(1)
- C5
Pt. 3 modified (14.10.2008) by The Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), art. 34(1) (with art. 36(3))
- C6
Pt. 3 modified (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), art. 28(1)
- C7
Pt. 3 modified (27.8.2010) by The Llangollen and Corwen Railway Order 2010 (S.I. 2010/2136), art. 11(1)
- C8
Pt. 3 applied (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 47(1) (with art. 51, Sch. 10 paras. 68, 85)
- C9
Pt. 3 modified (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), arts. 1, 36(2)
- C10
Pt. 3 applied (5.4.2017) by The Keuper Underground Gas Storage Facility Order 2017 (S.I. 2017/433), arts. 1, 38(2)
- C11
Pt. 3 modified (11.1.2023) by The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022 (S.I. 2022/1406), arts. 1, 35(2) (with art. 34(2), Sch. 12 paras. 5, 47, 79)