Paragraph M.2 Conditions

Development is permitted by Class M subject to the following conditions—

(a)

the development is within the curtilage of an existing school, college, university F1, prison or hospital;

(b)

the development is only used as part of, or for a purpose incidental to, the use of that school, college, university , prison or hospital;

(c)

any new building erected is, in the case of article 2(3) land, constructed using materials which have a similar external appearance to those used for the original school, college, university , prison or hospital buildings; F2...

(d)

any extension or alteration is, in the case of article 2(3) land, constructed using materials which have a similar external appearance to those used for the building being extended or altered F3;

(e)

where proposed development under Class M relates to the erection, extension or alteration of a school building that results in an increase in the school’s published admission number, the developer must, within a period of six months starting with the date the development is completed, submit to the local planning authority a travel plan for the site;

(f)

where proposed development under Class M relates to the erection, extension or alteration of a university building, development is permitted subject to the condition that before beginning the development the developer applies to the local planning authority for a determination as to whether the prior approval of the authority will be required as to—

(i)

transport and highways impacts of the proposed development;

(ii)

the design and external appearance of the erection, extension or alteration; or

(iii)

the impact of the development on heritage and archaeology;

(g)

an application required under paragraph (f) is to be made and determined in accordance with paragraph M.2A (procedure for applications for prior approval under Class M);

(h)

development approved pursuant to an application under paragraph (f) is permitted subject to the condition that it is completed within a period of three years starting with the prior approval F4date;

F5(i)

where proposed development under Class M relates to the erection, extension or alteration of an open prison building, before beginning development the developer must—

(i)

assess the contamination and flood risks of the development;

(ii)

identify measures to reduce, so far as practicable, any contamination or flood risks of the development;

(iii)

where the development is in an area within Flood Zone 3, carry out prior consultation in accordance with paragraph M.2B (procedure for prior consultation under Class M); and

(iv)

provide written notification to the local planning authority of the proposed development with the documents and information listed in sub-paragraph (j);

(j)

the documents and information specified in sub-paragraph (i)(iv) are—

(i)

a written description of the proposed development;

(ii)

a plan indicating the site and showing the proposed development;

(iii)

a drawing, prepared to an identified scale, showing—

(aa)

in the case of a building to be erected, the proposed external dimensions and elevations of that building; and

(bb)

in the case of a building to be extended or altered, the external dimensions and elevations of that building both before and after the proposed extension or alteration;

(iv)

the proposed commencement date;

(v)

written confirmation that development will not take place on any land used as a playing field, and remaining in that use, at any time in the 5 years before the proposed commencement date;

(vi)

the developer’s contact address; and

(vii)

the developer’s email address if the developer is content to receive communications electronically.

Annotations

Textual amendments

F1

Word in Sch. 2 Pt. 7 Class M para. M.2 inserted (21.4.2021) by The Town and Country Planning (General Permitted Development etc.) (England) (Amendment) Order 2021 (S.I. 2021/428), arts. 1(1), 9(5)(a) (with art. 15(3))

F2

Word in Sch. 2 Pt. 7 Class M para. M.2(c) omitted (21.4.2021) by virtue of The Town and Country Planning (General Permitted Development etc.) (England) (Amendment) Order 2021 (S.I. 2021/428), arts. 1(1), 9(5)(b) (with art. 15(3))

F3

Sch. 2 Pt. 7 Class M para. M.2(e)-(h) inserted (21.4.2021) by The Town and Country Planning (General Permitted Development etc.) (England) (Amendment) Order 2021 (S.I. 2021/428), arts. 1(1), 9(5)(c) (with art. 15(1)(a)(3))

F4

Word in Sch. 2 Pt. 7 para. M.2(h) substituted (21.12.2023) by The Town and Country Planning (General Permitted Development etc.) (England) (Amendment) (No. 2) Order 2023 (S.I. 2023/1279), arts. 1(1), 3(3)(a)

F5

Sch. 2 Pt. 7 para. M.2(i)(j) inserted (21.12.2023) by The Town and Country Planning (General Permitted Development etc.) (England) (Amendment) (No. 2) Order 2023 (S.I. 2023/1279), arts. 1(1), 3(3)(b)

Notes on Class M – extensions etc for schools, colleges, universities , prisons and hospitals

Textual amendments

F1

Word in Sch. 2 Pt. 7 Class M heading inserted (21.4.2021) by The Town and Country Planning (General Permitted Development etc.) (England) (Amendment) Order 2021 (S.I. 2021/428), arts. 1(1), 9(2) (with art. 15(3))