OpenLegislation

Paragraph I.2 ConditionsF1F2

Development is permitted by Class I subject to the following conditions—

(a)

the anemometry mast must, so far as practicable, be sited so as to minimise its effect on the amenity of the area;

(b)

the developer must, within 7 days of commencing development, notify the local planning authority in writing of the development and its location; and

(c)

on or before the expiry of a period of twelve months beginning with the date on which the development began, the anemometry mast must be removed.

Annotations

Textual amendments

F1

Order revoked (E.) (15.4.2015) by The Town and Country Planning (General Permitted Development) (England) Order 2015 (S.I. 2015/596), art. 1(1), Sch. 4 para. 1 (with arts. 1(2), 8(2)(3))

F2

Sch. 2 Pt. 40 substituted (W.) (18.6.2012) by The Town and Country Planning (General Permitted Development) (Amendment) (Wales) Order 2012 (S.I. 2012/1346), arts. 1(1), 2(3)