Paragraph 2 Applications made under RequirementsI1

England, Wales and Scotland

Where an application has been made to the relevant planning authority for any consent, agreement or approval required under a Requirement, the relevant planning authority must give notice to the undertaker of its decision on the application including the reasons within a period of 8 weeks beginning with—

(a)

the day immediately following that on which the application is received by the authority; or

(b)

such longer period as may be agreed by the undertaker and the relevant planning authority.