Paragraph 2 Applications made under RequirementsI1
England, Wales and Scotland
Where an application has been made to the relevant planning authority for any consent, agreement or approval required under a Requirement, the relevant planning authority must give notice to the undertaker of its decision on the application including the reasons within a period of 8 weeks beginning with—
(a)
the day immediately following that on which the application is received by the authority; or
(b)
such longer period as may be agreed by the undertaker and the relevant planning authority.
Annotations
Commencement
- I1
Sch. 11 para. 2 in force at 27.9.2016, see art. 1(2)