Paragraph 10 Pre-construction plans and documentation: time for submission, etc.I1

England, Wales and Scotland

(1)

Each plan, programme, scheme or statement required to be approved under Condition 7 or 9 must be submitted for approval at least 4 months before the intended start of construction, except where otherwise stated or unless otherwise agreed in writing by the MMO.

(2)

No licensed marine activities may be commenced until the MMO has approved in writing each plan, programme, scheme or statement required to be approved under Condition 7 or 9; and the licensed marine activities must, where relevant, be carried out in accordance with the approved plan, programme, scheme or statement unless otherwise agreed in writing by the MMO (after consultation with every person required to be consulted before approval of the original plan, programme, scheme or statement).