Paragraph 10 Pre-construction plans and documentationI1

England, Wales and Scotland

(1)

Each programme, statement, plan, protocol or scheme required to be approved under condition 9 shall be submitted for approval at least four months prior to the intended start of construction, except where otherwise stated or unless otherwise agreed in writing by the MMO.

(2)

The licensed activities shall be carried out in accordance with the approved plans, protocols, statements, schemes and details approved under condition 9, unless otherwise agreed in writing by the MMO.

(3)

No part of this licence authorises any part of the authorised scheme extending beyond the detailed design parameters at conditions 1 to 5.