Paragraph 169 Notice of worksI1

England and Wales As made

The undertaker must provide to the IOT Operators a minimum of 28 days’ notice prior to commencing any relevant work in order that an engineer can be made available to observe the relevant works and, when required, advise on the necessary safety precautions. The IOT Operators will be entitled to watch and inspect the execution of the relevant works at any time.

Annotations

Commencement

I1

Sch. 9 para. 169 in force at 1.5.2025, see art. 1(2)