Paragraph 185 Authorisation of works details affecting pipelines or protected crossingsI1
England and Wales As made
Before commencing any part of a relevant work, the undertaker must submit the works details to Air Products in accordance with paragraph 195.
The works details submitted under sub-paragraph (1) will be treated as having been received by Air Products on the date—
that the undertaker obtains written acknowledgement of receipt from Air Products; or
two clear working days following the date that the work details were submitted under sub-paragraph (1),
whichever is earliest.
The undertaker must as soon as reasonably practicable provide such further particulars as Air Products may, within 30 days from receipt of the works details under sub-paragraph (2), reasonably require.
Annotations
Commencement
- I1
Sch. 9 para. 185 in force at 1.5.2025, see art. 1(2)