Paragraph 33 Construction hoursI1
England and Wales
Construction work for the connection works and any construction-related traffic movements to or from the site of the relevant works must not take place other than between 0700 hours and 1900 hours Monday to Friday, 0700 hours and 1400 hours on Saturdays, with no activity on Sundays or bank holidays, save—
where continuous periods of operation are required, such as concrete pouring and drilling;
for the delivery of abnormal loads to the relevant works, which may cause congestion on the local road network;
where works are being carried out on the foreshore;
or unless otherwise agreed with the relevant planning authority in accordance with sub-paragraph (2).
All construction operations which are to be undertaken outside the hours specified in sub-paragraph (1) must be agreed with the relevant planning authority in advance, and shall be carried out within the agreed times.
Annotations
Commencement
- I1
Sch. 1 Pt. 3 para. 33 in force at 28.11.2014, see art. 1