Part 2 SUBSTITUTE AND SUPPLEMENTARY DOCUMENTSI1
England and Wales
(1) Originating Document | (2) Replacement or supplementary part | (3) Document reference | (4) Date | (5) Examination library reference |
|---|---|---|---|---|
| Environmental Statement | Chapter 7: Climate Change | EX1/WB6.2.7_A | November 2023 | [REP1-012] |
| Environmental Statement | Chapter 23: Summary of Significant Effects | EX3/WB6.2.23_B | January 2024 | [REP3-010] |
| Environmental Statement | Appendix 5.1: Site Selection Assessment | WB6.3.5.1_A | May 2023 | [AS-004] |
| Environmental Statement | Appendix 9.7: Great Crested Newt Survey Report | EX1/WB6.3.9.7_A | November 2023 | [REP1-020] |
| Environmental Statement | Appendix 14.1: Transport Assessment | EX4/WB6.3.14.1 _C | February 2024 | [REP4-036] |
| Environmental Statement | Non-Technical Summary | EX6/WB6.5_B | April 2024 | [REP6-011] |
| Environmental Statement | Interrelationship with Other National Infrastructure Projects | EX6/WB8.1.9_D | April 2024 | [REP6-015] |
| Environmental Statement | Technical Note on Cumulative Effects of Additional Schemes | EX4/WB8.2.5_B | May 2024 | F1[REP7-016] |
| Environmental Statement | Technical Note on Horizontal Directional Drilling and Cabling under the River Trent | EX4/WB8.2.8 | February 2024 | [REP4-074] |
| Environmental Statement | ES Addendum 13.1: Archaeological Trial Trenching Evaluation Fieldwork Report for the Shared Cable Corridor | EX4/WB8.4.13.1 | February 2024 | [REP4-076] |
| Environmental Statement | ES Addendum: Air Quality Impact Assessment of BESS Fire | EX3/WB8.4.17.1 | January 2024 | [REP3-040] |
| Environmental Statement | ES Addendum 21.1: Human Health and Wellbeing Effects | EX4/WB8.4.21.1 | February 2024 | [REP4-077] |
| Environmental Statement | ES Addendum 23.1: Cumulative Effects | EX5/WB8.4.23.1 | April 2024 | [REP5-015] |
| Environmental Statement | Environmental statement appendix 9.12 biodiversity net gain report | EN010132/DEC/WB6.3.9.12_A | November 2024 | N/A |
| Environmental Statement | Figure 8.18.3: Landscape and Ecology Mitigation and Enhancement Measures West Burton 3 | EN10132/DEC/6.4.8.18.3_B | October 2024 | N/A |
Annotations
Textual amendments
- F1
Words in Sch. 13 Pt. 2 inserted (4.6.2025) by The West Burton Solar Project (Correction) Order 2025 (S.I. 2025/647), art. 1(1), Sch. 1 Table
Commencement
- I1
Sch. 13 Pt. 2 in force at 15.2.2025, see art. 1