Paragraph 220 I1
England and Wales
In this Part—
“apparatus” means the cables, structures or other infrastructure owned, occupied or maintained by Tillbridge or its successor in title within the F1Tillbridge Work No. 4E;
“construction” includes execution, placing, altering, replacing, reconstruction, relaying, maintenance, extensions, enlargement and removal; and “construct” and “constructed” must be construed accordingly;
“plans” includes sections, drawings, specifications, designs, design data, software, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of the Tillbridge Work No. 4E; and
“specified works” means so much of any works of operations authorised by this Order (or authorised by any planning permission intended to operate in conjunction with this Order) as is—
- (a)
within the Tillbridge Work No. 4E;
- (b)
in, on, under, over or within 25 metres of the Tillbridge Work No. 4E or any apparatus; or
- (c)
may in any way adversely affect any apparatus.
- (a)
“Tillbridge” means an undertaker with the benefit of all or part of the Tillbridge Solar Order for the time being;
“ Tillbridge Work No. 4E ” means the area for Work No. 4E authorised in the Tillbridge Solar Order;
Annotations
Textual amendments
- F1
Words in Sch. 15 Pt. 17 substituted (4.6.2025) by The West Burton Solar Project (Correction) Order 2025 (S.I. 2025/647), art. 1(1), Sch. 1 Table
Commencement
- I1
Sch. 15 para. 220 in force at 15.2.2025, see art. 1