Article 7 Limits of deviationI1

England, Wales and Scotland

In carrying out, maintaining or diverting the authorised development, the undertaker may—

(a)

deviate Works No. 1, 2, 3(f), 3(k), 4, 5 and 6 laterally from the lines or situations of the authorised development shown on the works plans within the extent of the limits of deviation shown on those plans; and

(b)

deviate Works No. 1 and 2 vertically—

(i)

upwards to a limit of not less than 1.1 metres below the surface of the ground; and

(ii)

to any extent downwards as may be found to be necessary or practical to a maximum depth of 70 metres below the surface of the ground,

except that sub-paragraph (i) does not apply to those parts of Works No. 1 and 2 that are built within the Yoxall AGI site, where such works may deviate upwards to a limit of 2.8 metres above ground level;

(c)

deviate or place Works No. 3, 4, 5 and 6 vertically upwards or above ground level to the height limits set for each of these works in Part 1 of Schedule 1.