Paragraph 17 Project wide conditionsI1

England and Wales

(1)

Prior to any works commencing below the level of high water, the undertaker must submit detailed method statements to the MMO for approval for each operation of the licensed activities at least 3 months prior to the commencement of such licensed activity and any such approval must not be unreasonably withheld or delayed and is deemed to have been permitted if it is neither given nor refused within 3 months of the specified day.

(2)

The undertaker must provide the MMO with such further details as the MMO may reasonably require, any such request to be made within 28 days from the day on which the detailed method statement was submitted under sub-paragraph (1).

(3)

In this paragraph the “specified day” means—

(a)

the day on which the MMO have received the detailed method statement referred to in sub-paragraph (1); or

(b)

the day on which the undertaker provides the MMO with such further particulars as have been reasonably requested by the MMO under sub-paragraph (2).

Annotations

Commencement

I1

Sch. 5 para. 17 in force at 10.8.2016, see art. 1