Paragraph 18 Project wide conditionsI1
England and Wales
(1)
The undertaker must only work and access the licensed area within a defined and marked out area so as to limit personnel and plant access to the area of Works Nos. 2 and 3.
(2)
Co-ordinates (in WGS84) and plan diagrams of the licensed area and access routes must be submitted to the MMO at least 4 weeks prior to the commencement of the licensed activity.
(3)
Licensed activity must not commence before the approval of the co-ordinates and plan diagrams of the licensed area and access routes has been given by the MMO.
Annotations
Commencement
- I1
Sch. 5 para. 18 in force at 10.8.2016, see art. 1