Paragraph 34 Capital dredging, disposal conditions and debrisI1
England and Wales
The undertaker must agree a capital dredge and disposal strategy with the MMO at least 4 weeks before the commencement of any licensed activities.
If any disposal or dredging activities are to take place after 1st October 2017—
the undertaker must submit a sediment sampling plan to the MMO for approval at least 6 months prior to that dredging or disposal activity being carried out;
the sediment sampling and analysis of the sediment must be completed by a laboratory validated by the MMO at least 6 weeks prior to the dredging or disposal activity being carried out; and
the dredging and disposal activity must not be carried out without the consent of the MMO.
Annotations
Commencement
- I1
Sch. 5 para. 34 in force at 10.8.2016, see art. 1