Paragraph 5 Authorisation of works details affecting pipelines or protected crossingsI1

England and Wales

No part of a relevant work is to be commenced until one of the following conditions has been satisfied—

(a)

the works details supplied in respect of that relevant work under paragraph 4 have been authorised by the owner and operator of all the affected assets; or

(b)

the works details supplied in respect of that relevant work under paragraph 4 have been authorised by an expert under paragraph 7(3); or

(c)

authorisation is deemed to have been given in accordance with paragraph 7(1).

Annotations

Commencement

I1

Sch. 9 para. 5 in force at 10.8.2016, see art. 1