OpenLegislation

Paragraph 26 Control of artificial light emissionsI1

England, Wales and Scotland

(1)

F1The Project A converter station works must not be brought into operation until a written scheme for the management and mitigation of artificial light emissions during the operation of Work No. 7 has been submitted to and approved in writing by the relevant planning authority following consultation with the relevant statutory nature conservation body.

(2)

The approved scheme for the management and mitigation of artificial light emissions F2under paragraph (1) must be implemented and maintained during the operation of the F3Project A onshore works.

F4(3)

 The Project B converter station works must not be brought into operation until a written scheme for the management and mitigation of artificial light emissions during the operation of the Project B converter station works has been submitted to and approved by the relevant planning authority following consultation with the relevant statutory nature conservation body.

(4)

The approved scheme for the management and mitigation of artificial light emissions under paragraph (3) must be implemented and maintained during the operation of the Project B onshore works.

Annotations

Textual amendments

F1

Words in Sch. 1 para. 26(1) substituted (21.11.2025) by The Dogger Bank Creyke Beck Offshore Wind Farm (Amendment) Order 2025 (S.I. 2025/1264), arts. 1, 10(a)

F2

Words in Sch. 1 para. 26(2) inserted (21.11.2025) by The Dogger Bank Creyke Beck Offshore Wind Farm (Amendment) Order 2025 (S.I. 2025/1264), arts. 1, 10(b)(i)

F3

Words in Sch. 1 para. 26(2) inserted (21.11.2025) by The Dogger Bank Creyke Beck Offshore Wind Farm (Amendment) Order 2025 (S.I. 2025/1264), arts. 1, 10(b)(ii)

F4

Sch. 1 para. 26(3)(4) inserted (21.11.2025) by The Dogger Bank Creyke Beck Offshore Wind Farm (Amendment) Order 2025 (S.I. 2025/1264), arts. 1, 10(c)

Commencement

I1

Sch. 1 para. 26 in force at 11.3.2015, see art. 1