Paragraph 12 I1
(1)
Within Work Nos. 1A and 2A, the HVDC cable crossings must not, in total, exceed—
(a)
16 in number;
(b)
88,450 cubic metres in volume of cable crossing material;
(c)
98,100 square metres in seabed footprint.
(2)
Within Work Nos. 1B and 2B, the HVDC cable crossings must not, in total, exceed—
(a)
16 in number;
(b)
88,450 cubic metres in volume of cable crossing material;
(c)
98,100 square metres in seabed footprint.
Annotations
Commencement
- I1
Sch. 1 Pt. 3 para. 12 in force at 26.8.2015, see art. 1