Regulation 16 Authorisation requirements for the renewal or upgrading of fixed installations
In respect of a project for the renewal or upgrading of a fixed installation, the project entity must apply to the DFI for a decision as to whether an authorisation is required.
An application made under paragraph (1) is invalid unless it is accompanied by the following information—
a file setting out details of the project,
the project entity’s assessment of whether there are any new or changed safety risks resulting from the works envisaged and how any such risks will be managed, and
an indication of any TSI, or part of a TSI, with which there may be non-compliance following the renewal or upgrade.
Within the period of one month beginning with the day after the day on which the application is received, the DFI must respond in writing and confirm—
that the application is complete, or
what supplementary information is required for the completion of the application, together with a reasonable deadline within which to provide it.
The project entity must provide the DFI with such supplementary information requested under paragraph (3) as the project entity is reasonably able to supply and the project entity must give an explanation in writing where the information requested is not supplied.
In making a decision as to the requirement for authorisation, the DFI must consider factors including—
the extent to which the overall safety level of the fixed installation concerned may be adversely affected by the works envisaged;
whether the new authorisation is required by the TSIs;
any relevant requirements of the national implementation planf1;
any changes made to the values of the parameters referred to in regulation 10(5)(b) on the basis of which the existing authorisation was granted.
The DFI must make its decision as to the requirement for authorisation within the period of four months beginning with the day after the day on which the DFI receives a complete application.
Annotations
Footnotes
- f1
-
In defining the standards which must be met in order to meet the essential requirements, TSIs may require member States and Northern Ireland to produce a national implementation plan for how they plan to comply with a particular TSI.