Paragraph I1
England and Wales
Work No. 9 – temporary construction laydown areas including—
Work No. 9A – temporary construction laydown area comprising—
areas of hardstanding;
car parking;
pedestrian bridge including ducts for the carrying of electricity and other utility services;
site and welfare offices and workshops;
security infrastructure, including cameras, perimeter fencing and lighting;
site drainage and waste management infrastructure (including sewerage); and
electricity, water, waste water and telecommunications connections.
Work No. 9B – a temporary construction laydown area comprising—
areas of hardstanding;
security infrastructure, including cameras, perimeter fencing and lighting;
up to two means of access;
site drainage and waste management infrastructure (including sewerage);
car parking; and
electricity, water, waste water and telecommunications connections.
Annotations
Commencement
- I1
Sch. 1 in force at 25.10.2019, see art. 1