Paragraph I1
England and Wales
Work No. 4 – new gas insulated switchgear banking buildings including—
(a)
Work No. 4A (in connection with Unit X)—
(i)
a building containing gas insulated switchgear and other associated switch gear and ancillary equipment;
(ii)
a building containing control equipment;
(iii)
up to three sets of cable sealing ends; and
(iv)
ground raising and ground preparation works.
(b)
Work No. 4B (in connection with Unit Y)—
(i)
a building or an extension to the building in Work No. 4A containing gas insulated switchgear and other switch gear and ancillary equipment;
(ii)
up to three sets of cable sealing ends; and
(iii)
ground raising and ground preparation works.
Annotations
Commencement
- I1
Sch. 1 in force at 25.10.2019, see art. 1