Paragraph 6 I1
England, Wales and Scotland
The total length of the cables comprising Work No. 3A must not exceed F1400 kilometres for the HVDC option and 250 kilometres for the HVAC option.
The total length of the cables comprising Work No. 1(d) must not exceed F2680 kilometres for the HVDC option and 350 kilometres for the HVAC option.
The total amount of cable protection for the cables comprising Work No. 3A must not exceed F324,000 metres3 for the HVDC option and 15,000 metres3 for the HVAC option.
The total amount of cable protection for the cables comprising Work No. 1(d) must not exceed F43,000 metres3 for the HVDC option and 3,000 metres3 for the HVAC option.
Annotations
Textual amendments
- F1
Words in Sch. 1 Pt. 3 Requirement 6(1) substituted (25.3.2016) by The East Anglia ONE Offshore Wind Farm (Corrections and Amendments) Order 2016 (S.I. 2016/447), art. 1, Sch. 2
- F2
Words in Sch. 1 Pt. 3 Requirement 6(2) substituted (25.3.2016) by The East Anglia ONE Offshore Wind Farm (Corrections and Amendments) Order 2016 (S.I. 2016/447), art. 1, Sch. 2
- F3
Words in Sch. 1 Pt. 3 Requirement 6(3) substituted (25.3.2016) by The East Anglia ONE Offshore Wind Farm (Corrections and Amendments) Order 2016 (S.I. 2016/447), art. 1, Sch. 2
- F4
Words in Sch. 1 Pt. 3 Requirement 6(4) substituted (25.3.2016) by The East Anglia ONE Offshore Wind Farm (Corrections and Amendments) Order 2016 (S.I. 2016/447), art. 1, Sch. 2
Commencement
- I1
Sch. 1 Pt. 3 para. 6 in force at 7.7.2014, see art. 1