Paragraph 11 Stages and phasing of authorised development onshoreI1

England, Wales and Scotland

(1)

The connection works may not be commenced until a written scheme setting out the stages of the connection works has been submitted to, and approved by, the relevant planning authority

(2)

Work No. 67 may not be commenced until a written scheme setting out whether it is to be carried out in a single onshore phase or in two onshore phases has been submitted to, and approved by, the relevant planning authority.

(3)

In the event that Work No. 67 is to be carried out in two onshore phases, at least 14 days’ prior notice of commencement of the second onshore phase must be given to the relevant planning authority.

(4)

The written schemes specified in paragraphs (1) and (2) must be implemented as approved by the relevant planning authority.

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 11 in force at 29.8.2017, see art. 1