OpenLegislation

Equipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres Regulations (Northern Ireland) 1996

S.R. 1996/247 · Made 24 June 1996 · Extends to Northern Ireland

Not fully up to date. 75 changes made by later legislation have not yet been written into this text, which is revised to 24 June 1996.

See the changes not yet applied
ProvisionChangeMade by
reg. 16coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 7coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 8coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 9coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 10coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 11coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 12coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 13coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 14coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 15coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 6coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 17coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 18coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 19coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 20coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
Sch. 1coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
Sch. 2coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
Sch. 4coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
Sch. 5coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
Sch. 6coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
Sch. 7coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
Sch. 8coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
Sch. 9coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
Sch. 10coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
Sch. 11coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
Sch. 12coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 1coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 2coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 3coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 4coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 5coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
Sch. 3coming into forceEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1996 reg. 1(1)
reg. 1(2)substitutedElectrical Equipment for Explosive Atmospheres (Certification) 1998 reg. 4
reg. 12(8)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1999 reg. 3(b)
reg. 13(1)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1999 reg. 3(b)
reg. 14(2)(a)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1999 reg. 3(b)
reg. 15(2)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1999 reg. 3(b)
reg. 15(4)(a)(c)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1999 reg. 3(b)
Sch. 13 para. 1(a)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1999 reg. 3(b)
Sch. 13 para. 4words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1999 reg. 3(b)
reg. 13(1)words omittedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1999 reg. 3(c)
reg. 12(1)(2)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1999 reg. 3(b)
Sch. 13 para. 2(1)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1999 reg. 3(b)
reg. 2(2)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1999 reg. 3(a)
reg. 12(4)(5)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1999 reg. 3(b)
reg. 10(5)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 1999 reg. 3(b)
Sch. 2word substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(11)(e)
reg. 2(2)words insertedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(2)(a)(ii)(aa)
reg. 2(2)words insertedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(2)(a)(ii)(bb)
reg. 2(5)addedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(2)(b)
reg. 3(2)(a)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(3)(a)
reg. 3(2)(b)substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(3)(b)
reg. 6(1)words insertedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(4)
reg. 8(2)(b)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(5)
reg. 9words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(6)
reg. 11substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(7)
reg. 14(1)(b)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(8)
reg. 16substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(9)
Sch. 1 para. 5words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(10)(a)
Sch. 1 para. 9words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(10)(b)
Sch. 2word substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(11)(a)
Sch. 2word substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(11)(b)(i)
Sch. 2word substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(11)(b)(ii)
Sch. 2word substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(11)(c)
Sch. 2words insertedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(11)(d)(i)
Sch. 2word substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(11)(d)(ii)
reg. 2(2)words substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(2)(a)(i)
Sch. 3 para. 2(b)word insertedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(12)
Sch. 5 para. 5word substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(13)
Sch. 7 para. 4.1word substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(14)
Sch. 8 para. 2words omittedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(15)
Sch. 9 para. 3.1words omittedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(16)(a)
Sch. 9 para. 3.2word substitutedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2008 reg. 3(16)(b)
RegulationsrevokedEquipment and Protective Systems Intended for Use in Potentially Explosive Atmospheres 2017 Sch. 8
Blanket amendmentwords substitutedTreaty of Lisbon (Changes in Terminology) 2011 art. 3-6 8-10

HEALTH AND SAFETY

Made 24th June 1996

Coming into operation 29th July 1996

The Department of Economic Development, being a Department designatedf1 for the purposes of section 2(2) of the European Communities Act 1972f2 in relation to measures relating to equipment and protective systems intended for use in potentially explosive atmospheres, in exercise of the powers conferred on it by that section and of every other power enabling it in that behalf, hereby makes the following Regulations:

Annotations to the whole text

Footnotes

f1

S.I. 1995/751

f2

1972 c. 68

Contents

  1. Part I: Preliminary Not yet in force
  2. 1Citation, commencement and revocations Not yet in force
  3. 2Interpretation Not yet in force
  4. Part II: Application Not yet in force
  5. 3Equipment, protective systems, devices and components Not yet in force
  6. 4Excluded equipment, protective systems, devices and components Not yet in force
  7. 5Exclusion until 30th June 2003 of equipment and protective systems complying with health and safety provisions in operation on 23rd March 1994 Not yet in force
  8. Part III: General Requirements Not yet in force
  9. 6General duty relating to the placing on the market of equipment, protective systems or devices by a responsible person Not yet in force
  10. 7General duty relating to the supply of equipment, protective systems or devices by a person other than the responsible person Not yet in force
  11. 8General duty relating to the placing on the market of components by a responsible person Not yet in force
  12. 9Exceptions to placing on the market in respect of certain equipment, protective systems, devices and components Not yet in force
  13. 10Conformity assessment procedures Not yet in force
  14. 11Notified bodies Not yet in force
  15. 12Notified bodies appointed by the Department Not yet in force
  16. 13Fees Not yet in force
  17. Part Supplementary Provisions Not yet in force
  18. 14Conditions for equipment, protective systems, devices and components being taken to comply with the provisions of the ATEX Directive Not yet in force
  19. Part IV: Enforcement Not yet in force
  20. 15Application of Schedule 13 Not yet in force
  21. 16Offences and penalties Not yet in force
  22. 17Defence of due diligence Not yet in force
  23. 18Liability of persons other than the principal offender Not yet in force
  24. 19Amendment of the Electricity at Work Regulations (Northern Ireland) 1991 Not yet in force
  25. 20Consequential amendment of the Provision and Use of Work Equipment Regulations (Northern Ireland) 1993 Not yet in force
  26. Signature
  27. Schedule 1: The CE marking and other inscriptions Not yet in force
  28. 1Paragraph 1 Not yet in force
  29. 2Paragraph 2 Not yet in force
  30. 3Paragraph 3 Not yet in force
  31. 4Paragraph 4 Not yet in force
  32. 5Paragraph 5 Not yet in force
  33. 6Paragraph 6 Not yet in force
  34. 7Paragraph 7 Not yet in force
  35. 8Paragraph 8 Not yet in force
  36. 9Paragraph 9 Not yet in force
  37. Schedule 2: Essential health and safety requirements relating to the design and construction of equipment and protective systems intended for use in potentially explosive atmospheres Not yet in force
  38. APreliminary observations Not yet in force
  39. BPreliminary observations Not yet in force
  40. 1Preliminary observations Not yet in force
  41. 1.0General requirements Not yet in force
  42. 1.0.1Principles of integrated explosion safety Not yet in force
  43. 1.0.2Principles of integrated explosion safety Not yet in force
  44. 1.0.3Special checking and maintenance conditions Not yet in force
  45. 1.0.4Surrounding area conditions Not yet in force
  46. 1.0.5Marking Not yet in force
  47. 1.0.6Instructions Not yet in force
  48. 1.1Selection of materials Not yet in force
  49. 1.1.1Selection of materials Not yet in force
  50. 1.1.2Selection of materials Not yet in force
  51. 1.1.3Selection of materials Not yet in force
  52. 1.2Design and construction Not yet in force
  53. 1.2.1Design and construction Not yet in force
  54. 1.2.2Design and construction Not yet in force
  55. 1.2.3Enclosed structures and prevention of leaks Not yet in force
  56. 1.2.4Dust deposits Not yet in force
  57. 1.2.5Additional means of protection Not yet in force
  58. 1.2.6Safe opening Not yet in force
  59. 1.2.7Protection against other hazards Not yet in force
  60. 1.2.8Overloading of equipment Not yet in force
  61. 1.2.9Flameproof enclosure systems Not yet in force
  62. 1.3Potential ignition sources Not yet in force
  63. 1.3.1Hazards arising from different ignition sources Not yet in force
  64. 1.3.2Hazards arising from static electricity Not yet in force
  65. 1.3.3Hazards arising from stray electric and leakage currents Not yet in force
  66. 1.3.4Hazards arising from overheating Not yet in force
  67. 1.3.5Hazards arising from pressure compensation operations Not yet in force
  68. 1.4Hazards arising from external effects Not yet in force
  69. 1.4.1Hazards arising from external effects Not yet in force
  70. 1.4.2Hazards arising from external effects Not yet in force
  71. 1.5Requirements in respect of safety-related devices Not yet in force
  72. 1.5.1Requirements in respect of safety-related devices Not yet in force
  73. 1.5.2Requirements in respect of safety-related devices Not yet in force
  74. 1.5.3Requirements in respect of safety-related devices Not yet in force
  75. 1.5.4Control and display units Not yet in force
  76. 1.5.5Requirements in respect of devices with a measuring function for explosion protection Not yet in force
  77. 1.5.6Requirements in respect of devices with a measuring function for explosion protection Not yet in force
  78. 1.5.7Requirements in respect of devices with a measuring function for explosion protection Not yet in force
  79. 1.5.8Risks arising from software Not yet in force
  80. 1.6Integration of safety requirements relating to the system Not yet in force
  81. 1.6.1Integration of safety requirements relating to the system Not yet in force
  82. 1.6.2Integration of safety requirements relating to the system Not yet in force
  83. 1.6.3Hazards arising from power failure Not yet in force
  84. 1.6.4Hazards arising from connections Not yet in force
  85. 1.6.5Placing of warning devices as parts of equipment Not yet in force
  86. 2Placing of warning devices as parts of equipment Not yet in force
  87. 2.0Requirements applicable to equipment in category M of equipment-group I Not yet in force
  88. 2.0.1Requirements applicable to equipment in category M 1 of equipment-group I Not yet in force
  89. 2.0.1.1Requirements applicable to equipment in category M 1 of equipment-group I Not yet in force
  90. 2.0.1.2Requirements applicable to equipment in category M 1 of equipment-group I Not yet in force
  91. 2.0.1.3Requirements applicable to equipment in category M 1 of equipment-group I Not yet in force
  92. 2.0.1.4Requirements applicable to equipment in category M 1 of equipment-group I Not yet in force
  93. 2.0.2Requirements applicable to equipment in category M 2 of equipment-group I Not yet in force
  94. 2.0.2.1Requirements applicable to equipment in category M 2 of equipment-group I Not yet in force
  95. 2.0.2.2Requirements applicable to equipment in category M 2 of equipment-group I Not yet in force
  96. 2.0.2.3Requirements applicable to equipment in category M 2 of equipment-group I Not yet in force
  97. 2.1Requirements applicable to equipment in category 1 of equipment-group II Not yet in force
  98. 2.1.1Explosive atmospheres caused by gases, vapours or hazes Not yet in force
  99. 2.1.1.1Explosive atmospheres caused by gases, vapours or hazes Not yet in force
  100. 2.1.1.2Explosive atmospheres caused by gases, vapours or hazes Not yet in force
  101. 2.1.1.3Explosive atmospheres caused by gases, vapours or hazes Not yet in force
  102. 2.1.2Explosive atmospheres caused by air/dust mixtures Not yet in force
  103. 2.1.2.1Explosive atmospheres caused by air/dust mixtures Not yet in force
  104. 2.1.2.2Explosive atmospheres caused by air/dust mixtures Not yet in force
  105. 2.1.2.3Explosive atmospheres caused by air/dust mixtures Not yet in force
  106. 2.1.2.4Explosive atmospheres caused by air/dust mixtures Not yet in force
  107. 2.2Requirements for category 2 of equipment-group II Not yet in force
  108. 2.2.1Explosive atmospheres caused by gases, vapours or mists Not yet in force
  109. 2.2.1.1Explosive atmospheres caused by gases, vapours or mists Not yet in force
  110. 2.2.1.2Explosive atmospheres caused by gases, vapours or mists Not yet in force
  111. 2.2.1.3Explosive atmospheres caused by gases, vapours or mists Not yet in force
  112. 2.2.2Explosive atmospheres caused by air/dust mixtures Not yet in force
  113. 2.2.2.1Explosive atmospheres caused by air/dust mixtures Not yet in force
  114. 2.2.2.2Explosive atmospheres caused by air/dust mixtures Not yet in force
  115. 2.2.2.3Explosive atmospheres caused by air/dust mixtures Not yet in force
  116. 2.2.2.4Explosive atmospheres caused by air/dust mixtures Not yet in force
  117. 2.3Requirements applicable to equipment in category 3 of equipment-group II Not yet in force
  118. 2.3.1Explosive atmospheres caused by gases, vapours or mists Not yet in force
  119. 2.3.1.1Explosive atmospheres caused by gases, vapours or mists Not yet in force
  120. 2.3.1.2Explosive atmospheres caused by gases, vapours or mists Not yet in force
  121. 2.3.2Explosive atmospheres caused by air/dust mixtures Not yet in force
  122. 2.3.2.1Explosive atmospheres caused by air/dust mixtures Not yet in force
  123. 2.3.2.2Explosive atmospheres caused by air/dust mixtures Not yet in force
  124. 2.3.2.3Explosive atmospheres caused by air/dust mixtures Not yet in force
  125. 3SUPPLEMENTARY REQUIREMENTS IN RESPECT OF PROTECTIVE SYSTEMS Not yet in force
  126. 3.0General requirements Not yet in force
  127. 3.0.1General requirements Not yet in force
  128. 3.0.2General requirements Not yet in force
  129. 3.0.3General requirements Not yet in force
  130. 3.0.4General requirements Not yet in force
  131. 3.1Planning and design Not yet in force
  132. 3.1.1Characteristics of materials Not yet in force
  133. 3.1.2Characteristics of materials Not yet in force
  134. 3.1.3Characteristics of materials Not yet in force
  135. 3.1.4Characteristics of materials Not yet in force
  136. 3.1.5Pressure-relief systems Not yet in force
  137. 3.1.6Explosion suppression systems Not yet in force
  138. 3.1.7Explosion decoupling systems Not yet in force
  139. 3.1.8Explosion decoupling systems Not yet in force
  140. Schedule 3: Criteria determining the classification of equipment-groups into categories Not yet in force
  141. 1Equipment-group I Not yet in force
  142. 2Equipment-group II Not yet in force
  143. Schedule 4Excluded equipment, protective systems and devices Not yet in force
  144. Schedule 5: Module: EC type-examination Not yet in force
  145. 1Paragraph 1 Not yet in force
  146. 2Paragraph 2 Not yet in force
  147. 3Paragraph 3 Not yet in force
  148. 4Paragraph 4 Not yet in force
  149. 4.1Paragraph 4.1 Not yet in force
  150. 4.2Paragraph 4.2 Not yet in force
  151. 4.3Paragraph 4.3 Not yet in force
  152. 4.4Paragraph 4.4 Not yet in force
  153. 5Paragraph 5 Not yet in force
  154. 6Paragraph 6 Not yet in force
  155. 7Paragraph 7 Not yet in force
  156. 8Paragraph 8 Not yet in force
  157. 9Paragraph 9 Not yet in force
  158. Schedule 6: Module: Production quality assurance Not yet in force
  159. 1Paragraph 1 Not yet in force
  160. 2Paragraph 2 Not yet in force
  161. 3Quality system Not yet in force
  162. 3.1Quality system Not yet in force
  163. 3.2Quality system Not yet in force
  164. 3.3Quality system Not yet in force
  165. 3.4Quality system Not yet in force
  166. 4Surveillance under the responsibility of the notified body Not yet in force
  167. 4.1Surveillance under the responsibility of the notified body Not yet in force
  168. 4.2Surveillance under the responsibility of the notified body Not yet in force
  169. 4.3Surveillance under the responsibility of the notified body Not yet in force
  170. 4.4Surveillance under the responsibility of the notified body Not yet in force
  171. 5Surveillance under the responsibility of the notified body Not yet in force
  172. 6Surveillance under the responsibility of the notified body Not yet in force
  173. Schedule 7: Module: Product verification Not yet in force
  174. 1Paragraph 1 Not yet in force
  175. 2Paragraph 2 Not yet in force
  176. 3Paragraph 3 Not yet in force
  177. 4Verification by examination and testing of each piece of equipment Not yet in force
  178. 4.1Verification by examination and testing of each piece of equipment Not yet in force
  179. 4.2Verification by examination and testing of each piece of equipment Not yet in force
  180. 4.3Verification by examination and testing of each piece of equipment Not yet in force
  181. Schedule 8: Module: Conformity to type Not yet in force
  182. 1Paragraph 1 Not yet in force
  183. 2Paragraph 2 Not yet in force
  184. 3Paragraph 3 Not yet in force
  185. Schedule 9: Module: Product quality assurance Not yet in force
  186. 1Paragraph 1 Not yet in force
  187. 2Paragraph 2 Not yet in force
  188. 3Quality system Not yet in force
  189. 3.1Quality system Not yet in force
  190. 3.2Quality system Not yet in force
  191. 3.3Quality system Not yet in force
  192. 3.4Quality system Not yet in force
  193. 4Surveillance under the responsibility of the notified body Not yet in force
  194. 4.1Surveillance under the responsibility of the notified body Not yet in force
  195. 4.2Surveillance under the responsibility of the notified body Not yet in force
  196. 4.3Surveillance under the responsibility of the notified body Not yet in force
  197. 4.4Surveillance under the responsibility of the notified body Not yet in force
  198. 5Surveillance under the responsibility of the notified body Not yet in force
  199. 6Surveillance under the responsibility of the notified body Not yet in force
  200. Schedule 10: Module: Internal control of production Not yet in force
  201. 1Paragraph 1 Not yet in force
  202. 2Paragraph 2 Not yet in force
  203. 3Paragraph 3 Not yet in force
  204. 4Paragraph 4 Not yet in force
  205. 5Paragraph 5 Not yet in force
  206. Schedule 11: Module: Unit verification Not yet in force
  207. 1Paragraph 1 Not yet in force
  208. 2Paragraph 2 Not yet in force
  209. 3Paragraph 3 Not yet in force
  210. Schedule 12Content of the EC declaration of conformity Not yet in force
  211. Schedule 13: Enforcement Not yet in force
  212. 1Enforcement in relation to relevant products Not yet in force
  213. 2Forfeiture Not yet in force
  214. 4Duty of Department to inform Secretary of State of action taken Not yet in force
  215. 5Savings Not yet in force
  216. 6Interpretation Not yet in force
  217. Explanatory note