Appendix ANNEX F: TRAFFIC OPERATION AND MANAGEMENT SUBSYSTEM ASSESSMENT GUIDELINESF1

United Kingdom Repealed

Original text. Later amendments are not shown.

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

1.

This annex sets out guidelines to facilitate assessments by Member States to confirm that the operational process(es) proposed:

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

2.

The Infrastructure Manager or Railway Undertaking concerned must supply the Member State with appropriate documentation (as described in clause 3 below) describing the new or amended operations process(es).

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

3.

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

3.1.

The documentation describing the operational process(es) concerned should contain at least the following elements:

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

3.2.

The Member State shall:

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

4.

The assessment report shall include at least the following information:

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Annotations

Textual amendments

F1

Repealed by Commission Decision of 12 May 2011 concerning the technical specification for interoperability relating to the ‘operation and traffic management’ subsystem of the trans-European conventional rail system (notified under document C(2011) 3099) (Text with EEA relevance) (2011/314/EU).