Paragraph 32 Operational traffic routing and management planI1
England, Wales and Scotland
The authorised development must not be commissioned until a written operational traffic routing and management plan has been submitted to and, after consultation with the relevant highway authorities, approved by the planning authority.
The plan submitted and approved must be in accordance with the principles set out in chapter 7 of the environmental statement and the operational travel plan framework contained in Appendix 7C to the environmental statement.
The plan submitted and approved must include details of the routes to be used for the transport of fuel, consumables and combustion by-products to and from the authorised development.
The plan must be implemented as approved.
Annotations
Commencement
- I1
Sch. 2 para. 32 in force at 19.11.2015, see art. 1(2)