Paragraph 28 Construction code of practiceI1

England, Wales and Scotland

No part of the connection works or the transmission works shall be commenced until a construction code of practice relating to the relevant part of the relevant works has been submitted to and, after consultation with the highway authority and Natural England, approved by the relevant planning authority in relation to the relevant part of the relevant works. The code shall cover all the subject areas set out in the final draft code submitted as part of the examination and as certified by the Secretary of State and any other matters the relevant planning authority reasonably requires. The code approved in relation to the relevant part of the relevant works shall be followed in relation to those works, unless otherwise agreed by the relevant planning authority.

Annotations

Commencement

I1

Sch. 1 para. 28 in force at 15.6.2013, see art. 1