Paragraph 36 Onshore decommissioningI1

England, Wales and Scotland

Upon the cessation of commercial operation of the connection works or the transmission works, a scheme for the demolition and removal of the relevant works (in whole or in part), and the final proposed condition of the relevant land, including a proposed timetable, shall be submitted to and approved by the relevant planning authority, in consultation with Natural England. The proposed scheme shall be based on the onshore decommissioning statement submitted with the application. The scheme shall be carried out in accordance with the approved details, unless otherwise agreed by the relevant planning authority.

Annotations

Commencement

I1

Sch. 1 para. 36 in force at 15.6.2013, see art. 1