Paragraph 13 Seasonal restrictionsI1
England, Wales and Scotland
No piling of monopile foundations or other foundation piling in the course of construction of the authorised scheme shall take place in array area C during the relevant peak sole spawning season (the maximum period being 1st April to 15th May), unless otherwise agreed with the MMO, following consultation with Natural England and JNCC.
No piling of monopile foundations or other foundation piling in the course of construction of the authorised scheme shall take place in array area B during the relevant peak herring spawning season (the maximum period being 1st November to 31st December), unless otherwise agreed with the MMO, following consultation with Natural England and JNCC.
Annotations
Commencement
- I1
Sch. 2 para. 13 in force at 15.6.2013, see art. 1