Site Preparation Plans Site Preparation PlansF1

Drawing numberRevDrawing titleScale>Paper size
HPCSPW002a Rev101Site Layout Plan1:3500A1
HPCSPW002b00Beach Access Road Plan and Cross Sections1:250 / 1:50A1
HPCSPW004 Rev101Planning Application Fencing Arrangement (Sheet 1 of 3)1:3500A1
HPCSPW005 Rev101Fencing Enlarged Detail West (Sheet 2 of 3)1:1500A1
HPCSPW006 Rev101Fencing Enlarged Detail East (Sheet 3 of 3)1:1500A1
HPCSPW007 Rev101Indicative Earthworks Cut and Fill Arrangement1:3500A1
HPCSPW00800Early Works Water Management Zone1:2500A1
HPCSP009 Rev101Surface Water Catchment Area Overall General Arrangement1:3000A1
HPCSPW01000Arrangement of Construction Drainage Outfall to Foreshore1:75A1
HPCSPW011 Rev101Surface Water Drainage Holford Stream Culvert1:1500 / 1:150A1
HPCSPW012a00Deep Water Drainage Arrangement1:2000 / 1:100A1
HPCSPW012b00Deep Water Arrangement Spine Drain Sections A and B1:200A1
HPCSPW012c00Deep Water Assessment Spine Drain Sections C1:200A1
HPCSPW013b00Typical Cross Section Through Haul Road1:50A1
HPCSPW0140011kv Sub Station Plan and Elevations1:100A1
HPCSPW01500Raw Water Reservoir Plans and Sections1:150A1
HPCSPW016 Rev101Surface Water Drainage in the Built Development Areas1:1750A1
HPCSPW01700Site Access Control Arrangement, Floor and Elevation1:50A1
HPCSPW019 Rev101Landscape Proposal Plan1:5000A1
HPCSPW02200Proposed Sewage Treatment Plant – Plans and Sections1:100A1
HPCSPW023a00Existing and Reinstated Ground Level Cross Sections1:2500 / 1:500A1
HPCSPW023b00Earthworks Platforms Cross Sections1:2500 / 1:500A1
HPCSPW025a Rev202Tree and Hedgerow Retention and Removal1:4000A1
HPCSPW025b Rev101Proposed Advanced Planting, Plan1:1000A1
HPCSPW02600Primary and Secondary Access Tracks1:3500A1
HPCSPW02700NW Boundary Mitigation During Construction Cross Sections A and B1:200A1
HPCSPW02800NW Boundary Mitigation During Construction Cross Sections C and D1:200A1
HPCSPW02900NW Boundary Mitigation During Construction Planting Plan1:750A1