Paragraph 10 Aviation safetyI1
England and Wales
The undertaker must exhibit such lights, with such shape, colour and character as are required in writing by Air Navigation Order 2016 M1 and determined necessary for aviation safety in consultation with the Defence Infrastructure Organisation Safeguarding and as directed by the Civil Aviation Authority
The undertaker must notify the Defence Infrastructure Organisation Safeguarding, and the MMO, at least 14 days prior to the commencement of the authorised project, in writing of the following information—
the date of the commencement of construction of the authorised project;
the date any wind turbine generators are brought into use;
the maximum height of any construction equipment to be used;
the maximum heights of any wind turbine generator and offshore accommodation platform to be constructed;
the latitude and longitude of each wind turbine generator and offshore accommodation platform to be constructed,
and the Defence Infrastructure Organisation Safeguarding must be notified of any changes to the information supplied under this paragraph and of the completion of the construction of the authorised project.
Annotations
Marginal citations
- M1
Commencement
- I1
Sch. 11 Pt. 2 para. 10 in force at 22.1.2021, see art. 1
Notes on the whole SI
Textual amendments
- F1
Preamble: bracket omitted (21.5.2021) by virtue of The Hornsea Three Offshore Wind Farm (Correction) Order 2021 (S.I. 2021/599), art. 1(2), Sch.