Paragraph 9 I1
England and Wales
(1)
The undertaker must colour all structures yellow (colour code RAL 1023) from at least highest astronomical tide to a height directed by Trinity House, or must colour the structure as directed by Trinity House from time to time.
(2)
Subject to sub-paragraph (1) above, unless the MMO otherwise directs, the undertaker must ensure that the wind turbine generators are painted light grey (colour code RAL 7035).
Annotations
Commencement
- I1
Sch. 11 Pt. 2 para. 9 in force at 22.1.2021, see art. 1
Notes on the whole SI
Textual amendments
- F1
Preamble: bracket omitted (21.5.2021) by virtue of The Hornsea Three Offshore Wind Farm (Correction) Order 2021 (S.I. 2021/599), art. 1(2), Sch.