Regulation 12 Pre-application meetingsI1

England and Wales

(1)

A developer may make a written request for a pre-application meeting with a planning authority, Natural Resources Wales or the Welsh Ministers (as the case may be).

(2)

Where a planning authority, Natural Resources Wales or the Welsh Ministers (as the case maybe) receive a request for a pre-application meeting, they must give notice to the person who made the request, within 15 days of the day on which the request is received, confirming whether or not a meeting will be held.

Annotations

Commencement

I1

Reg. 12 in force at 15.12.2025, see reg. 1