Paragraph 10 Fencing and other means of enclosureI1
England, Wales and Scotland
No phase of the solar farm works and grid connection works may commence until written details of all proposed temporary fences, walls or other means of enclosure (including those set out in the construction environmental management plan), for that phase have been submitted to and approved by the relevant planning authority or, where the phase falls within the administrative areas of both Braintree District Council and Chelmsford City Council, both relevant planning authorities.
No phase of the solar farm works and grid connection works may commence until written details of all permanent fences, walls or other means of enclosure for that phase (which must be substantially in accordance with the relevant outline design principles) have been submitted to and approved by the relevant planning authority or, where the phase falls within the administrative areas of both Braintree District Council and Chelmsford City Council, both relevant planning authorities.
For the purposes of sub-paragraph (1), “commence” includes any permitted preliminary works.
Any construction site must remain securely fenced in accordance with the approved details under sub-paragraph (1) at all times during construction of the solar farm works and grid connection works.
Any temporary fencing must be removed on completion of the phase of construction of the authorised development for which it was used.
Any approved permanent fencing in a phase must be completed before the date of final commissioning in respect of such phase.