OpenLegislation

Paragraph 11 Surface and foul water drainageI1

England, Wales and Scotland

(1)

No phase of the solar farm works and grid connection works may commence until written details of the surface water drainage scheme and (if any) foul water drainage system (which must be substantially in accordance with the outline drainage strategy) have been submitted to and approved by the relevant planning authority for that phase or, where the phase falls within the administrative areas of both Braintree District Council and Chelmsford City Council, both relevant planning authorities such approval to be in consultation with Essex County Council as the lead local flood authority.

(2)

Any approved scheme must be implemented as approved and maintained throughout the construction and operation of the solar farm works and grid connection works.

Annotations

Commencement

I1

Sch. 2 para. 11 in force at 18.7.2023, see art. 1