Part 2 SOLAR FARM WORKS AND GRID CONNECTION WORKS

England, Wales and Scotland

  1. 7Detailed design approval
  2. 8Battery safety management
  3. 9Landscape and ecological management plan
  4. 10Fencing and other means of enclosure
  5. 11Surface and foul water drainage
  6. 12Archaeology
  7. 13Construction environmental management plan
  8. 14Operational environmental management plan
  9. 15Construction traffic management plan
  10. 16Operational noise
  11. 17Permissive paths
  12. 18Public rights of way diversions
  13. 19Soils Management
  14. 20Decommissioning and restoration
  15. 21Highway improvements