Schedule 7 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKENI1

England and Wales

(1)

Plot reference Number shown on Land Plans

(2)

Purpose for which temporary possession may be taken

(3)

Relevant part of the authorised development

Land Plans – Sheet 1
1/1eRequired to provide a working area for improving the carriageway of the M60, installing gantries and utilities diversionsWork Nos. 03, 48 and 49 as shown on sheets 1 and 2 of the works plans
1/1fRequired to provide a working area for widening the carriageway of the M60, installing gantries and utilities diversionsWork Nos. 02, 45 and 48 as shown on sheets 1 and 2 of the works plans
1/1gRequired to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 03 as shown on sheets 1 and 2 of the works plans
1/1jRequired to provide a working area for improving the carriageway of the M60 and utilities diversionsWork No. 50 as shown on sheet 1 of the works plans
1/3cRequired to provide a working area for improving the carriageway of the M60 and utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/3dRequired to provide a working area for improving the carriageway of the M60 and utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/3eRequired to provide a working area for widening the carriageway of the M60, installing gantries and utilities diversionsWork Nos. 03, 48 and 49 as shown on sheets 1 and 2 of the works plans
1/3fRequired to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 03 as shown on sheets 1 and 2 of the works plans
1/3hRequired for utilities diversionsWork No. 50 as shown on sheet 1 of the works plans
1/5aRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5bRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5cRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5dRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5eRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5fRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5gRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5hRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5iRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5jRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5kRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5lRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5mRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5nRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5oRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5pRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5qRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5rRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5sRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5tRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5uRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5vRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5wRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5xRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5yRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5zRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5aaRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5abRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5acRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5adRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5aeRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5afRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5agRequired to provide a working area for improving the carriageway of the M60, installing gantries and utilities diversionsWork Nos. 02, 45 and 48 as shown on sheets 1 and 2 of the works plans
1/5ahRequired for utilities diversionsWork No. 45 as shown on sheet 1 of the works plans
1/5aiRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5ajRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5akRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5alRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5amRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5anRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5aoRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5apRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5aqRequired to provide a working area for widening the carriageway of the M60, installing gantries and utilities diversionsWork Nos. 03 and 49 as shown on sheets 1 and 2 of the works plans
1/5arRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5asRequired to provide a working area for widening the carriageway of the M60, installing gantries and utilities diversionsWork Nos. 03 and 49 as shown on sheets 1 and 2 of the works plans
1/5atRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5auRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5avRequired for utilities diversionsWork Nos. 45 and 48 as shown on sheet 1 of the works plans
1/5awRequired for utilities diversionsWork Nos. 45 and 48 as shown on sheet 1 of the works plans
1/5axRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5ayRequired for utilities diversionsWork Nos. 48 and 49 as shown on sheet 1 of the works plans
1/5azRequired for utilities diversionsWork Nos. 48 and 49 as shown on sheet 1 of the works plans
1/5aaaRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5aabRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5aacRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5aadRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5aaeRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/5aafRequired for utilities diversionsWork Nos. 48 and 49 as shown on sheet 1 of the works plans
1/6aRequired for utilities diversionsWork No. 49 as shown on sheet 1 of the works plans
1/6dRequired to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 02 as shown on sheets 1 and 2 of the works plans
1/7Required for utilities diversionsWork No. 45 as shown on sheet 1 of the works plans
1/8aRequired for utilities diversionsWork Nos. 45 and 48 as shown on sheet 1 of the works plans
1/8bRequired to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/9Required to provide a working area for widening the carriageway of the M60, installing gantries and utilities diversionsWork Nos. 03, 48 and 49 as shown on sheets 1 and 2 of the works plans
1/10Required to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 03 as shown on sheets 1 and 2 of the works plans
1/11Required to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 03 as shown on sheets 1 and 2 of the works plans
1/12Required to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 03 as shown on sheets 1 and 2 of the works plans
1/13Required to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 03 as shown on sheets 1 and 2 of the works plans
1/14aRequired to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 03 as shown on sheets 1 and 2 of the works plans
1/14bRequired to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 03 as shown on sheets 1 and 2 of the works plans
1/14cRequired to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 03 as shown on sheets 1 and 2 of the works plans
1/15Required to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 03 as shown on sheets 1 and 2 of the works plans
1/16Required to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 03 as shown on sheets 1 and 2 of the works plans
1/17aRequired to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/17bRequired to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/17cRequired to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/17dRequired to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/17eRequired to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/18aRequired to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/18bRequired to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/18cRequired to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/19Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/20Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/22aRequired to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/22bRequired to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/23Required to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 03 as shown on sheets 1 and 2 of the works plans
1/24Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/25Required to provide a working area for widening g the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/26Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/27Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/28Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/29Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/30Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/31aRequired to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/31bRequired to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/32Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigationWork Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans
1/33aRequired to provide a working area for widening the carriageway of the M60 and installing gantriesWork No. 02 as shown on sheets 1 and 2 of the works plans
Land Plans – Sheet 2
2/1eRequired for provision of a temporary construction compoundAll works
2/2Required to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation and utilities diversionsWork Nos. 03, 07, 08, 11, 12, 13, 14, 15, and 16 as shown on sheets 1, 2 and 3 of the works plans
2/3aRequired to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation and utilities diversionsWork Nos. 03, 07, 08, 11, 12, 13, 14, 15, and 16 as shown on sheets 1, 2 and 3 of the works plans
2/3cRequired to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation and utilities diversionsWork Nos. 03, 07, 08, 11, 12, 13 and 14 as shown on sheets 1, 2 and 3 of the works plans
2/4aRequired to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation and utilities diversionsWork Nos. 03, 07, 08, 11, 12, 13, 14, 15, and 16 as shown on sheets 1, 2 and 3 of the works plans
2/5aRequired to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation and environmental mitigationWork Nos. 02, 05, 06, 09, 10, 27, 29 and 57 as shown on sheets 1 and 2 of the works plans
2/5bRequired for provision of a temporary construction compoundAll works
2/5eRequired for provision of a temporary construction compoundAll works
2/5iRequired for provision of a temporary construction compoundAll works
2/6Required for utilities diversionsWork No. 52 as shown on sheet 2 of the works plans
2/7aRequired for utilities diversionsWork No. 52 as shown on sheet 2 of the works plans
2/7bRequired for utilities diversionsWork No. 52 as shown on sheet 2 of the works plans
2/8bRequired to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation and utilities diversionsWork Nos. 03, 07, 08, 11, 12, 13 and 14 as shown on sheets 1, 2 and 3 of the works plans
2/8eRequired to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation, environmental mitigation and utilities diversionsWork Nos. 03, 07, 08, 11, 12, 13, 14, 15, 16, 17, 25, 51 and 58 as shown on sheets 1, 2 and 3 of the works plans
2/11Required to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation, environmental mitigation and utilities diversionsWork Nos. 03, 07, 08, 11, 12, 13, 14, 15, 16, 17, 25, 51 and 58 as shown on sheets 1, 2 and 3 of the works plans
2/12Required for utilities diversionsWork No. 51 as shown on sheet 2 of the works plans
2/16fRequired to provide access for landscaping works drainage attenuation and environmental mitigationWork Nos. 37 and 38 as shown on sheet 2 of the works plans
Land Plans – Sheet 4
4/8bRequired for provision of a temporary construction compound and material storage areaWork Nos. 43, 44 and 47 as shown on sheet 4 of the works plans