Schedule 7 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKENI1
England and Wales
| (1) Plot reference Number shown on Land Plans | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development |
|---|---|---|
| Land Plans – Sheet 1 | ||
| 1/1e | Required to provide a working area for improving the carriageway of the M60, installing gantries and utilities diversions | Work Nos. 03, 48 and 49 as shown on sheets 1 and 2 of the works plans |
| 1/1f | Required to provide a working area for widening the carriageway of the M60, installing gantries and utilities diversions | Work Nos. 02, 45 and 48 as shown on sheets 1 and 2 of the works plans |
| 1/1g | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 03 as shown on sheets 1 and 2 of the works plans |
| 1/1j | Required to provide a working area for improving the carriageway of the M60 and utilities diversions | Work No. 50 as shown on sheet 1 of the works plans |
| 1/3c | Required to provide a working area for improving the carriageway of the M60 and utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/3d | Required to provide a working area for improving the carriageway of the M60 and utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/3e | Required to provide a working area for widening the carriageway of the M60, installing gantries and utilities diversions | Work Nos. 03, 48 and 49 as shown on sheets 1 and 2 of the works plans |
| 1/3f | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 03 as shown on sheets 1 and 2 of the works plans |
| 1/3h | Required for utilities diversions | Work No. 50 as shown on sheet 1 of the works plans |
| 1/5a | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5b | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5c | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5d | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5e | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5f | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5g | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5h | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5i | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5j | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5k | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5l | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5m | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5n | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5o | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5p | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5q | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5r | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5s | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5t | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5u | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5v | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5w | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5x | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5y | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5z | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5aa | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5ab | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5ac | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5ad | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5ae | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5af | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5ag | Required to provide a working area for improving the carriageway of the M60, installing gantries and utilities diversions | Work Nos. 02, 45 and 48 as shown on sheets 1 and 2 of the works plans |
| 1/5ah | Required for utilities diversions | Work No. 45 as shown on sheet 1 of the works plans |
| 1/5ai | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5aj | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5ak | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5al | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5am | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5an | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5ao | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5ap | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5aq | Required to provide a working area for widening the carriageway of the M60, installing gantries and utilities diversions | Work Nos. 03 and 49 as shown on sheets 1 and 2 of the works plans |
| 1/5ar | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5as | Required to provide a working area for widening the carriageway of the M60, installing gantries and utilities diversions | Work Nos. 03 and 49 as shown on sheets 1 and 2 of the works plans |
| 1/5at | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5au | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5av | Required for utilities diversions | Work Nos. 45 and 48 as shown on sheet 1 of the works plans |
| 1/5aw | Required for utilities diversions | Work Nos. 45 and 48 as shown on sheet 1 of the works plans |
| 1/5ax | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5ay | Required for utilities diversions | Work Nos. 48 and 49 as shown on sheet 1 of the works plans |
| 1/5az | Required for utilities diversions | Work Nos. 48 and 49 as shown on sheet 1 of the works plans |
| 1/5aaa | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5aab | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5aac | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5aad | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5aae | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/5aaf | Required for utilities diversions | Work Nos. 48 and 49 as shown on sheet 1 of the works plans |
| 1/6a | Required for utilities diversions | Work No. 49 as shown on sheet 1 of the works plans |
| 1/6d | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 02 as shown on sheets 1 and 2 of the works plans |
| 1/7 | Required for utilities diversions | Work No. 45 as shown on sheet 1 of the works plans |
| 1/8a | Required for utilities diversions | Work Nos. 45 and 48 as shown on sheet 1 of the works plans |
| 1/8b | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/9 | Required to provide a working area for widening the carriageway of the M60, installing gantries and utilities diversions | Work Nos. 03, 48 and 49 as shown on sheets 1 and 2 of the works plans |
| 1/10 | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 03 as shown on sheets 1 and 2 of the works plans |
| 1/11 | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 03 as shown on sheets 1 and 2 of the works plans |
| 1/12 | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 03 as shown on sheets 1 and 2 of the works plans |
| 1/13 | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 03 as shown on sheets 1 and 2 of the works plans |
| 1/14a | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 03 as shown on sheets 1 and 2 of the works plans |
| 1/14b | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 03 as shown on sheets 1 and 2 of the works plans |
| 1/14c | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 03 as shown on sheets 1 and 2 of the works plans |
| 1/15 | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 03 as shown on sheets 1 and 2 of the works plans |
| 1/16 | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 03 as shown on sheets 1 and 2 of the works plans |
| 1/17a | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/17b | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/17c | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/17d | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/17e | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/18a | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/18b | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/18c | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/19 | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/20 | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/22a | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/22b | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/23 | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 03 as shown on sheets 1 and 2 of the works plans |
| 1/24 | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/25 | Required to provide a working area for widening g the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/26 | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/27 | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/28 | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/29 | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/30 | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/31a | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/31b | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/32 | Required to provide a working area for widening the carriageway of the M60, installing gantries and environmental mitigation | Work Nos. 02, 54 and 55 as shown on sheets 1 and 2 of the works plans |
| 1/33a | Required to provide a working area for widening the carriageway of the M60 and installing gantries | Work No. 02 as shown on sheets 1 and 2 of the works plans |
| Land Plans – Sheet 2 | ||
| 2/1e | Required for provision of a temporary construction compound | All works |
| 2/2 | Required to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation and utilities diversions | Work Nos. 03, 07, 08, 11, 12, 13, 14, 15, and 16 as shown on sheets 1, 2 and 3 of the works plans |
| 2/3a | Required to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation and utilities diversions | Work Nos. 03, 07, 08, 11, 12, 13, 14, 15, and 16 as shown on sheets 1, 2 and 3 of the works plans |
| 2/3c | Required to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation and utilities diversions | Work Nos. 03, 07, 08, 11, 12, 13 and 14 as shown on sheets 1, 2 and 3 of the works plans |
| 2/4a | Required to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation and utilities diversions | Work Nos. 03, 07, 08, 11, 12, 13, 14, 15, and 16 as shown on sheets 1, 2 and 3 of the works plans |
| 2/5a | Required to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation and environmental mitigation | Work Nos. 02, 05, 06, 09, 10, 27, 29 and 57 as shown on sheets 1 and 2 of the works plans |
| 2/5b | Required for provision of a temporary construction compound | All works |
| 2/5e | Required for provision of a temporary construction compound | All works |
| 2/5i | Required for provision of a temporary construction compound | All works |
| 2/6 | Required for utilities diversions | Work No. 52 as shown on sheet 2 of the works plans |
| 2/7a | Required for utilities diversions | Work No. 52 as shown on sheet 2 of the works plans |
| 2/7b | Required for utilities diversions | Work No. 52 as shown on sheet 2 of the works plans |
| 2/8b | Required to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation and utilities diversions | Work Nos. 03, 07, 08, 11, 12, 13 and 14 as shown on sheets 1, 2 and 3 of the works plans |
| 2/8e | Required to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation, environmental mitigation and utilities diversions | Work Nos. 03, 07, 08, 11, 12, 13, 14, 15, 16, 17, 25, 51 and 58 as shown on sheets 1, 2 and 3 of the works plans |
| 2/11 | Required to provide a working and material storage area for widening the carriageway of the M60 and installing gantries, temporary haul routes, drainage attenuation, environmental mitigation and utilities diversions | Work Nos. 03, 07, 08, 11, 12, 13, 14, 15, 16, 17, 25, 51 and 58 as shown on sheets 1, 2 and 3 of the works plans |
| 2/12 | Required for utilities diversions | Work No. 51 as shown on sheet 2 of the works plans |
| 2/16f | Required to provide access for landscaping works drainage attenuation and environmental mitigation | Work Nos. 37 and 38 as shown on sheet 2 of the works plans |
| Land Plans – Sheet 4 | ||
| 4/8b | Required for provision of a temporary construction compound and material storage area | Work Nos. 43, 44 and 47 as shown on sheet 4 of the works plans |