Paragraph 3 Detailed designI1

England, Wales and Scotland

(1)

The authorised development must be carried out in accordance with—

(a)

the approved plans listed in Table 1 below inclusive of any limits of deviation; and

(b)

any other plans, drawings, documents, details, schemes, statements or strategies which are approved by the relevant planning authority pursuant to any requirement (as the same may be amended by approval of the relevant planning authority pursuant to requirement 19(1))—

Table 1

works plans

Submission document reference number 2.3

access rights of way plan

Submission document reference number 2.4

(2)

The authorised development must not exceed the maximum parameters specified in Table 2 and Table 3 below (as the same may be amended by approval of the relevant planning authority under requirement 19(1))—

Table 2

(1)

Element of authorised development

(2)

Maximum height

(metres) above a site level of approximately 99 metres AOD

(3)

Maximum width

(metres)

(4)

Maximum length

(metres)

(5)

Other parameters

Gas turbine building (part of numbered work 1A)25 metres45 metres60 metresMaximum height 124m AOD
Each Heat Recovery Steam Generator Building (part of numbered work 1A)35 metres13 metres25 metresMaximum height AOD 134 metres
Each exhaust gas emission flue stack (part of numbered work 1A)50 metres––Maximum height AOD 149 metres Maximum diameter 6.5 metres
Steam turbine building (part of numbered work 1A)21 metres26 metres45 metres–
Air cooled condenser (part of numbered work 1A)26 metres48 metres48 metres–
Switchgear room (part of numbered work 1A)5 metres10 metres15 metres–
Raw/fire water storage tank (part of numbered work 1B)20 metres––Maximum diameter 15 metres
Each water storage tank (part of numbered work 1B)20 metres––Maximum diameter 5 metres
Water treatment system (part of numbered work 1B)10 metres25 metres20 metres–
Workshop (part of numbered work 1B)10 metres20 metres30 metres–
Natural gas pressure regulating installation (PRI) (part of numbered work 1B)5 metres25 metres35 metres–
Administration/ control building (part of numbered work 1C)10 metres10 metres20 metres–
Heat network interface building (part of numbered work 1C)15 metres20 metres30 metres–
Each transformer compound (part of numbered work 1D)8 metres15 metres15 metres–
132kV switchyard (part of work numbered 1D)10 metres42 metres72 metres–
Perimeter fencing (part of numbered work 1E)2.5 metres–770 metres–

Table 3

(1)

Element of authorised development

(2)

Maximum height

(metres) above the existing site level

(3)

Maximum width

(metres)

(4)

Maximum length

(metres)

(5)

Other parameters

Above Ground Installation (numbered work 2A)2.5 metres13 metres13 metres–
Pipeline inspection gauge facility (part of numbered work 2A)1.6 metres1 metre5.5 metres–
Perimeter fencing (part of numbered work 2A)2.5 metres–52 metres–
Pipeline support plinth including crown of pipe (part of numbered work 2B)2 metres0.8 metres1.4 metres–
(3)

To the extent that design objectives relating to any numbered work are set out in the design objectives statement, that numbered work must be designed substantially in accordance with the relevant design objective set out therein.

(4)

Numbered works 1, 2 and 4 may not commence until, for that numbered work, written details have been submitted to and approved by the relevant planning authority (in consultation with the National Trust regarding the external appearance and the colour of all permanent buildings and structures) concerning—

(a)

the siting, design, external appearance, dimensions and floor levels of all permanent buildings and structures; and

(b)

the colour, materials and surface finishes of the pipeline and all permanent buildings and structures.

(5)

The details to be submitted for approval under sub-paragraph (4) must include appropriately scaled plans and sectional drawings.

Annotations

Commencement

I1

Sch. 2 para. 3 in force at 2.8.2016, see art. 1

Notes on the whole SI

Textual amendments

F1

Words in Preamble substituted (22.11.2016) by The Meaford Gas Fired Generating Station (Correction) Order 2016 (S.I. 2016/1046), arts. 1, 2, Sch.