Paragraph 1 Test loadsI1

Northern Ireland

(1)

Every repaired meter shall be tested at each of the loads specified in Table 2, except that test number 2 in that Table may be omitted.

(2)

Every new meter shall be calibrated and tested at a sufficient number of load points so as to ensure that meter errors are not greater than the limits specified in paragraph 9.

(3)

A test for starting will also be carried out on new meters in accordance with test number 7 of Table 2.

(4)

The ratio errors shall be determined for voltage transformers that are intended for use with meters but are not tested with a meter.

(5)

Current transformers intended for use with meters but not tested with a meter shall be tested from 5% to 120% of rated current.

Annotations

Commencement

I1

Sch. 1 para. 1n2 in operation at 1.2.1999, see reg. 1