Paragraph 21 Deployment of new cable protection and scour protectionI1

England, Wales and Scotland As made

Any cable protection and scour protection (other than the replenishment or replacement of existing cable protection or scour protection) authorised under this licence must be deployed within ten years from the date on which operation of the authorised project commences unless otherwise agreed by the MMO.

Annotations

Commencement

I1

Sch. 6 Pt. 2 para. 21 in force at 23.12.2025, see art. 1