Regulation 6 Class A: new renewable power stationsI1
England and Wales
(1)
Class A consists of any hereditament in relation to which the conditions in paragraph (2) are fulfilled.
(2)
The conditions mentioned in paragraph (1) are that—
(a)
the hereditament is a renewable power station;
(b)
the hereditament is first entered onto a local non-domestic rating list for the area of a billing authority in England on or after 1st April 2013; and
(c)
neither Schedule 1 or 2 applies.
Annotations
Commencement
- I1
Reg. 6 in force at 18.2.2013, see reg. 1(1)