No part of the authorised development shall be carried out until a written scheme providing for the monitoring of noise generated during the construction of the authorised development has been submitted to and approved by the relevant planning authority; the scheme shall specify—

(a)

the locations at which noise will be monitored;

(b)

the method of noise measurement (which shall accord with BS 5228 or, an equivalent successor standard or other agreed noise measurement methodology appropriate to the circumstances); and

(c)

the frequency of submission of data to the relevant planning authority.

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 18 in force at 2.10.2014, see art. 1