Paragraph 40 Drainage pondI1
England, Wales and Scotland
No works shall be carried out to remove or modify the northernmost pond in the operations area until details of the works to be carried out and a method statement for the carrying out of such works, to be prepared in consultation with C.RO Ports Killingholme Limited, the Environment Agency and North East Lindsey Drainage Board, have been submitted to and approved by the relevant planning authority.
The method statement shall detail protective works which will be carried out to ensure that no contaminants are mobilised by the works. The method statement shall also detail how the works will be carried out to ensure that there will be no detrimental effect on the performance of existing flood attenuation and thereafter once any modified pond is operational. The works shall be carried out in accordance with the approved details.
Annotations
Commencement
- I1
Sch. 1 Pt. 3 para. 40 in force at 2.10.2014, see art. 1