Part 2 Building heightsI1
England, Wales and Scotland
| F1(1) | (2) |
|---|---|
| Building | Height (metres) above ordnance datum |
| Heat recovery steam generator | 47 |
| Turbine hall | 35 |
| Main stack | 85 |
| Hybrid cooling tower (bank 1) | 28 |
| Hybrid cooling tower (bank 2) | 28 |
| Administration building | 17 |
| Warehouse | 25 |
| Water treatment plant | 13 |
| Break tank | 22 |
| Gas insulated switchgear building | 17 |
| Covered fuel storage | 40 |
| Biomass storage silos | 50 |
| Limestone storage silos | 50 |
| Gasifier, including fuel preparation facility | 70 |
| Air separation unit | 50 |
| Oxygen storage tank | 25 |
| nitrogen storage tank | 25 |
| Acid gas removal | 65 |
| Wastewater treatment plant | 25 |
| Electrical switching station 1 | 25 |
| Electrical switching station 2 | 15 |
| Electrical switching station 3 | 15 |
| Flare stack | 140 |
| Auxiliary boiler and stack | 15 |
Annotations
Textual amendments
- F1
Sch. 1 Pt. 2 table substituted (3.4.2026) by The North Killingholme (Generating Station) (Amendment) Order 2026 (S.I. 2026/445), arts. 1, 6
Commencement
- I1
Sch. 1 Pt. 2 in force at 2.10.2014, see art. 1