BuildingHeight (metres) above ordnance datum
Heat recovery steam generator47
Turbine hall35
Main stack85
Hybrid cooling tower (bank 1)28
Hybrid cooling tower (bank 2)28
Administration building17
Warehouse25
Water treatment plant13
Break tank22
Gas insulated switchgear building17
Covered fuel storage40
Biomass storage silos50
Limestone storage silos50
Gasifier, including fuel preparation facility70
Air separation unit50
Oxygen storage tank25
nitrogen storage tank25
Acid gas removal65
Wastewater treatment plant25
Electrical switching station 125
Electrical switching station 215
Electrical switching station 315
Flare stack140
Auxiliary boiler and stack15