Paragraph 13 I1
(1)
The licence holder must only work and access the works site within a defined and marked out area thereby limiting personnel and plant access to the site.
(2)
Co-ordinates (in WGS84) and plan diagrams of the work area and access routes must be submitted to the MMO at least 4 weeks prior to the commencement of works.
(3)
The written approval of the co-ordinates and plan diagrams by the MMO is required prior to works commencing.
Annotations
Commencement
- I1
Sch. 7 para. 13 in force at 2.10.2014, see art. 1