Paragraph 3
A description of—
(a)
the chosen design concept, including suitable diagrams, and a summary of the other design options which were considered;
(b)
how the chosen design concept is intended to ensure—
(i)
compliance with the requirements set out in regulations 5 and 10 of the Offshore Installations and Wells (Design and Construction, etc.) Regulations 1996 M1; and
(ii)
that risks with the potential to cause a major accident are reduced to the lowest level that is reasonably practicable; and
(c)
the criteria used to select the chosen design concept and the process by which the selection was made.
Annotations
Marginal citations
- M1
S.I. 1996/913, to which there is an amendment not relevant to these Regulations.