The Pressure Equipment (Safety) Regulations 2016
S.I. 2016/1105 · Made 15 November 2016 · Extends to United Kingdom
Consumer Protection
Health And Safety
Made 15th November 2016
Laid before Parliament 16th November 2016
Coming into force 8th December 2016
The Secretary of State is a Minister designated M1 for the purposes of section 2(2) of the European Communities Act 1972 M2 in relation to pressure equipment and assemblies of pressure equipment.
These Regulations make provision for a purpose mentioned in section 2(2) of the European Communities Act 1972 and it appears to the Secretary of State that it is expedient for certain references to provisions of EU instruments to be construed as references to those provisions as amended from time to time.
The Secretary of State makes these Regulations in exercise of the powers conferred by section 2(2) of, and paragraph 1A M3 of Schedule 2 to, the European Communities Act 1972.
Annotations to the whole text
Marginal citations
- M1
- M2
1972 c.68. Section 2(2) was amended by section 27(1)(a) of the Legislative and Regulatory Reform Act 2006 (c.51) and by Part 1 of the Schedule to the European Union (Amendment) Act 2008 (c.7). The enabling powers of section 2(2) were extended by virtue of the amendment of section 1(2) by section 1 of the European Economic Area Act 1993 (c.51).
- M3
Paragraph 1A of Schedule 2 was inserted by section 28 of the Legislative and Regulatory reform Act 2006 and amended by Part 1 of the Schedule to the European Union (Amendment) Act 2008.
Contents
- Part 1: Preliminary
- 1Citation and commencement
- 2Interpretation
- 2ADesignated standard
- 3Pressure equipment and assemblies
- 4Excluded pressure equipment and assemblies
- 5Exception for trade fairs, exhibitions and demonstrations
- 6Pressure equipment and assemblies subject to essential safety requirements
- 7Regulation 7
- 8Requirement for pressure equipment and assemblies to comply with sound engineering practice
- 8APower to reclassify pressure equipment and assemblies
- Part 2: Obligations of economic operators
- Chapter: Manufacturers
- 9Design and manufacture in accordance with essential safety requirements
- 10Technical documentation and conformity assessment
- 11Declaration of conformity and UK marking
- 12Duty to keep technical documentation and ... declaration of conformity
- 13Labelling of pressure equipment and assemblies
- 14Instructions and safety information
- 15Compliance procedures for series production
- 16Monitoring
- 17Duty to take action in respect of pressure equipment or assemblies placed on the market which are considered not to be in conformity
- 18Provision of information and cooperation
- 19Manufacturer's authorised representatives
- Chapter: Importers
- 20Prohibition on placing on the market pressure equipment or assemblies which are not in conformity
- 21Requirements which must be satisfied before an importer places pressure equipment or assemblies on the market
- 22Prohibition on placing on the market pressure equipment or assemblies considered not to be in conformity with the essential safety requirements
- 23Information identifying importer
- 24Instructions and safety information
- 25Storage and transport
- 26Monitoring
- 27Duty to take action in respect of pressure equipment or assemblies placed on the market considered not to be in conformity
- 28Retention of technical documentation and ... declaration of conformity
- 29Provision of information and cooperation
- Chapter: Distributors
- 30Duty to act with due care
- 31Requirements which must be satisfied before a distributor makes pressure equipment or assemblies available on the market)
- 32Storage and transport
- 33Prohibition on making available on the market where pressure equipment or assemblies are not considered to be in conformity with essential safety requirements
- 34Duty to take action in respect of pressure equipment made available on the market which are not in conformity
- 35Provision of information and cooperation
- Chapter: All economic operators
- 36Cases in which obligations of manufacturers apply to importers and distributors
- 37Translation of ... declaration of conformity
- 38Identification of economic operators
- 39Prohibition on improper use of UK marking
- 39AObligations which are met by complying with the obligations in the Directive
- 39BConformity assessment procedure obligation which is met by complying with the Directive.
- 39CFurther use of the UK marking
- 39DQualifying Northern Ireland Goods
- Part 3: Conformity assessment
- 40Presumption of conformity
- 41Conformity assessment procedures
- 42Regulation 42
- 42APower to amend applicable module
- 43Regulation 43
- 44Regulation 44
- 45Regulation 45
- 46Regulation 46
- 47Regulation 47
- 48... Declaration of conformity
- 49UK marking
- 49AUK(NI) indication
- 49BRegister of notified bodies established in the United Kingdom
- 50European approval for materials
- Part 4: Notification of conformity assessment bodies
- 51Approved bodies
- 52Recognised third party organisations
- 53User inspectorates
- 54Approval of conformity assessment bodies
- 55Approval of approved bodies
- 56Approval of recognised third party organisations
- 57Approval of user inspectorates
- 58Presumption of conformity of conformity assessment bodies
- 59Monitoring
- 60Restriction, suspension or withdrawal of approval (approved bodies and recognised third party organisations)
- 61Restriction, suspension or withdrawal of approval (user inspectorates)
- 62Operational matters in relation to approved bodies, recognised third party organisations and user inspectorates
- 63Subsidiaries and contractors
- 64Register of approved bodies
- 65United Kingdom Accreditation Service
- Part 5: Market surveillance and enforcement
- 66Designation of market surveillance authority
- 67Enforcement
- 68Enforcement powers
- 69Exercise of enforcement powers
- 70Evaluation of pressure equipment or assemblies presenting a risk
- 71Enforcement action in respect of pressure equipment or assemblies which are not in conformity and which present a risk
- 72EU safeguard procedure
- 73Pressure equipment or assemblies which are in conformity, but present a risk
- 74Enforcement action in cases of formal non-compliance
- 75Restrictive measures
- 76Offences
- 77Penalties
- 78Defence of due diligence
- 79Liability of persons other than principal offender
- 80Time limit for prosecution of offences
- 81Service of documents
- 82Recovery of expenses of enforcement
- 83Action by enforcing authority
- 84Appeals against notices
- 85Appropriate court for appeals against notices
- 86Compensation
- Part 6: Miscellaneous
- 87Review
- 88Transitional provisions
- 88ATransitional provision in relation to EU Exit
- 89Regulation 89
- 90Revocations, amendments and savings
- 91Regulation 91
- Signature
- Schedule 1: Excluded Pressure Equipment and Assemblies
- 1Paragraph 1
- Schedule 1A: Conformity Assessment Procedures for Pressure Equipment and Assemblies
- Part 1: Module A: Internal Production Control
- 1General
- 2Technical documentation
- 3Manufacturing
- 4UK marking and declaration of conformity
- 5Authorised representative
- Part 2: Module A2: Internal production control plus supervised pressure equipment checks at random
- 6General
- 7Technical documentation
- 8Manufacturing
- 9Final assessment and pressure equipment, assembly, checks
- 10UK marking and declaration of conformity
- 11Authorised representative
- Part 3: Module B: Type examination
- Type examination–production type
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- 16Paragraph 16
- 17Paragraph 17
- 18Paragraph 18
- 19Paragraph 19
- 20Paragraph 20
- 21Paragraph 21
- 22Paragraph 22
- 23Paragraph 23
- 24Paragraph 24
- 25Paragraph 25
- 26Paragraph 26
- 27Paragraph 27
- Type examination–design type
- 28Paragraph 28
- 29Paragraph 29
- 30Paragraph 30
- 31Paragraph 31
- 32Paragraph 32
- 33Paragraph 33
- 34Paragraph 34
- 35Paragraph 35
- 36Paragraph 36
- 37Paragraph 37
- 38Paragraph 38
- 39Paragraph 39
- 40Paragraph 40
- 41Paragraph 41
- 42Paragraph 42
- 43Paragraph 43
- 44Paragraph 44
- Part 4: Module C2: Conformity to type based on internal production control plus supervised pressure equipment checks at random intervals
- 45General
- 46Manufacturing
- 47Final assessment and pressure equipment check
- 48UK marking and declaration of conformity
- 49Authorised representative
- Part 5: Module D: Conformity to type based on quality assurance in the production process
- 50General
- 51Manufacturing
- 52Quality system
- 53Surveillance under the responsibility of the approved body
- 54UK marking and declaration of conformity
- 55Authorised representative
- Part 6: Module D1: Quality assurance of the production process
- 56General
- 57Technical documentation
- 58Manufacturing
- 59Quality system
- 60Surveillance under the responsibility of the approved body
- 61UK marking and declaration of conformity
- 62Authorised representative
- Part 7: Module E: Conformity to type based on pressure equipment quality assurance
- 63General
- 64Manufacturing
- 65Quality system
- 66Surveillance under the responsibility of the approved body
- 67UK marking and declaration of conformity
- 68Authorised representative
- Part 8: Module E1: Quality assurance of final pressure equipment inspection and testing
- 69General
- 70Technical documentation
- 71Manufacturing
- 72Quality system
- 73Surveillance under the responsibility of the approved body
- 74UK marking and declaration of conformity
- 75Authorised representative
- Part 9: Module F: Conformity to type based on pressure equipment verification
- 76General
- 77Manufacturing
- 78Verification
- 79Verification of conformity by examination and testing of every item of pressure equipment or assembly
- 80UK marking and declaration of conformity
- 81Authorised representative
- Part 10: Module G: Conformity based on unit verification
- 82General
- 83Technical documentation
- 84Manufacturing
- 85Verification
- 86UK marking and declaration of conformity
- 87Authorised representative
- Part 11: Module H: Conformity based on full quality assurance
- 88General
- 89Manufacturing
- 90Quality system
- 91Surveillance under the responsibility of the approved body
- 92UK marking and declaration of conformity
- 93Authorised representative
- Part 12: Module H1: Conformity based on full quality assurance plus design examination
- 94General
- 95Manufacturing
- 96Quality system
- 97Design examination
- 98Surveillance under the responsibility of the approved body
- 99UK marking and declaration of conformity
- 100Authorised representative
- Schedule 1B: Conformity Assessment Tables
- 1Paragraph 1
- 1AParagraph 1A
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- Schedule 2: Essential Safety Requirements
- Part 1: GENERAL
- 1Paragraph 1
- 2Paragraph 2
- Part 2: DESIGN
- 3General
- 4Design for adequate strength
- 5Calculation method
- 6Experimental design methods
- 7Provisions to ensure safe handling and operation
- 8Means of examination
- 9Means of draining and venting
- 10Corrosion or other chemical attack
- 11Wear
- 12Assemblies
- 13Provisions for filling and discharge
- 14Protection against exceeding the allowable limits of pressure equipment
- 15Safety accessories
- 16Pressure limiting devices
- 17Temperature monitoring devices
- 18External fire
- Part 3: MANUFACTURING
- 19Manufacturing procedures
- 20Preparation of the component parts
- 21Permanent joining
- 22Non-destructive tests
- 23Heat treatment
- 24Traceability
- 25Final assessment
- 26Final inspection
- 27Proof test
- 28Inspection of safety devices
- 29Marking and labelling
- 30Operating instructions
- Part 4: MATERIALS
- 31Paragraph 31
- Part 5: SPECIFIC PRESSURE EQUIPMENT REQUIREMENTS
- 32Paragraph 32
- 33Fired or otherwise heated pressure equipment with a risk of overheating as referred to in regulation 6
- 34Piping as referred to in regulation 6(c)
- Part 6: SPECIFIC QUANTITATIVE REQUIREMENTS FOR CERTAIN PRESSURE EQUIPMENT
- 35Paragraph 35
- 36Allowable stresses
- 37Paragraph 37
- 38Joint coefficients
- 39Pressure limiting devices, particularly for pressure vessels
- 40Hydrostatic test pressure
- 41Material characteristics
- Schedule 3
- Part 1: Classification of pressure equipment Classification of pressure equipment before IP completion day
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- Part 2: Classification of pressure equipment immediately on or after IP completion day
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- Schedule 4: Notified Approved body requirements
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- 16Paragraph 16
- 17Paragraph 17
- 18Paragraph 18
- Schedule 5: User inspectorate requirements
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- 16Paragraph 16
- Schedule 6: Operational obligations of notified approved bodies, recognised third party organisations and user inspectorates
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- Schedule 7: Enforcement powers of weights and measures authorities, district councils and the Secretary of State under the 1987 Act
- 1Enforcement powers under the 1987 Act
- 2Modifications to the 1987 Act
- Schedule 8: Enforcement powers of the Health and Safety Executive and the Office for Nuclear Regulation under the 1974 Act
- 1Enforcement powers under the 1974 Act
- 2Modifications to the 1974 Act
- Schedule 9: Enforcement powers of the Health and Safety Executive for Northern Ireland under the 1978 Order
- 1Enforcement powers under the 1978 Order
- 2Modifications to the 1978 Order
- Schedule 10: Compliance, withdrawal and recall notices
- 1Compliance notice
- 2Withdrawal notice
- 3Recall notice
- 4Interpretation
- Schedule 11: EU Declaration of Conformity
- 1... Declaration of conformity (No xxxx)
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- Schedule 12: Consequential amendments and revocations
- 1Amendment of the Provision and Use of Work Equipment Regulations 1998
- 2Amendment of the Provision and Use of Equipment at Work Regulations (Northern Ireland) 1999
- 3Amendment of the Pressure Systems Safety Regulations 2000
- 4Amendment of the Pressure Systems Safety Regulations (Northern Ireland) 2004
- 5Amendment of the Enterprise Act 2002 (Part 9 Restrictions on Disclosure of Information)(Specification) Order 2004
- 6Amendment of the Legislative and Regulatory Reform (Regulatory Functions) Order 2007
- 7Amendment of the Legislative Reform (Health and Safety Executive) Order 2008
- 8Amendment of the Supply of Machinery (Safety) Regulations 2008
- 9Amendment of the Co-ordination of Regulatory Enforcement (Regulatory Functions in Scotland and Northern Ireland) Order 2009
- 10Amendment of the Fluorinated Greenhouse Gases Regulations 2015
- 11Amendment of the Fluorinated Greenhouse Gases Regulations (Northern Ireland) 2015
- 12Amendment of the Consumer Rights Act 2015
- Explanatory note